11.
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
Answer: Option
Explanation:
B's 10 day's work = | ![]() |
1 | x 10 | ![]() |
= | 2 | . |
15 | 3 |
Remaining work = | ![]() |
1 - | 2 | ![]() |
= | 1 | . |
3 | 3 |
Now, | 1 | work is done by A in 1 day. |
18 |
![]() |
1 | work is done by A in | ![]() |
18 x | 1 | ![]() |
= 6 days. |
3 | 3 |
Discussion:
63 comments Page 4 of 7.
Priyanka Sengar said:
5 years ago
@All.
A=18
B=15
B=10
A=?
So 18:15::x:10
X = 12
12 ÷ 2 = 6.
A=18
B=15
B=10
A=?
So 18:15::x:10
X = 12
12 ÷ 2 = 6.
Harsha said:
5 years ago
Nice, Thanks @Siva.
AMAL RAJ R said:
4 months ago
A+ B = 30,
LCM = 30,
So Efficiency = 1.
That means A and B can do 1/2 work each on 1 day.
Therefore , for completing 30 units A will take 60 days.
LCM = 30,
So Efficiency = 1.
That means A and B can do 1/2 work each on 1 day.
Therefore , for completing 30 units A will take 60 days.
Raja said:
1 decade ago
LCM 90 brief explain?
Left the job B what mean?
Left the job B what mean?
Jay said:
1 decade ago
See, B complete his work in 15 days so split in 3 so we get 1:1:1.
Then he done the work of 10 days, so only last one remaining.1/3.
Now, A finish the whole work in 1/18. He need to done work in 1/3.
So 18*1/3 = 6 days.
Then he done the work of 10 days, so only last one remaining.1/3.
Now, A finish the whole work in 1/18. He need to done work in 1/3.
So 18*1/3 = 6 days.
UDAY.H.P said:
1 decade ago
Consider the full work to be done = 1
A can complete his work in 15 days but at the same speed he will work only for 10 days that is = 2/3
then the remaining work is = 1-(2/3)
A's working speed is =1/18 per day
that means aA can compleate this total work in 18 day
but the remaining work is 1/3 so 1/3*18 that is=6days
A can complete his work in 15 days but at the same speed he will work only for 10 days that is = 2/3
then the remaining work is = 1-(2/3)
A's working speed is =1/18 per day
that means aA can compleate this total work in 18 day
but the remaining work is 1/3 so 1/3*18 that is=6days
Siva said:
1 decade ago
Hi Guys,
A can complete work in 18 days
A's 1 day work = 1/18--------------(1)
B can complete work in 15 Days
B's 1 day work = 1/15--------------(2)
[but B is working 10 days only]
Remaining work is 5 days
so, remaining 1 day work is 5*(1/15) =>1/3
A's 1/3 work can complete in N days
so A's 1 day work = 1/3N--------------(3)
Equation=> (2)=(3)
1/3N = 1/18
so, N = 18/3
N = 6 Days
A's (1/3) remaining work can complete in 6 Days
N = 6 Days
A can complete work in 18 days
A's 1 day work = 1/18--------------(1)
B can complete work in 15 Days
B's 1 day work = 1/15--------------(2)
[but B is working 10 days only]
Remaining work is 5 days
so, remaining 1 day work is 5*(1/15) =>1/3
A's 1/3 work can complete in N days
so A's 1 day work = 1/3N--------------(3)
Equation=> (2)=(3)
1/3N = 1/18
so, N = 18/3
N = 6 Days
A's (1/3) remaining work can complete in 6 Days
N = 6 Days
Gayu said:
1 decade ago
Superb siva.
Kusum said:
1 decade ago
Can anyone explain this 1/3*18 ? please.
Md Ali Umar said:
1 decade ago
Hi @Kusum...........
We have to find how many days have to work to A for finishing the the remaining work. remaining work is 1/3
so we know the processes
. .
. A finishes 1/18 work in 1 day
.
. . ,, ,, 1 ,, ,, 1/(1/18) day
.
. . ,, ,, 1/3 ,, ,,1*(18/1)*(1/3)
After solving you well get 6days answer.
Understand???????????
We have to find how many days have to work to A for finishing the the remaining work. remaining work is 1/3
so we know the processes
. .
. A finishes 1/18 work in 1 day
.
. . ,, ,, 1 ,, ,, 1/(1/18) day
.
. . ,, ,, 1/3 ,, ,,1*(18/1)*(1/3)
After solving you well get 6days answer.
Understand???????????
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers