Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
351 comments Page 33 of 36.

Asshok said:   9 years ago
Why 1 - 7/15? Explain it.

Sagar said:   9 years ago
How to 300 come? Explain.

Gowtham said:   1 decade ago
How came remaining days?

Santhi said:   1 decade ago
Good explanation swetha.

Aadesh said:   9 years ago
28/60=14/30=7/15 @Pooja.

Swamy akunoori said:   1 decade ago
Good explanation anshu.

Pooja said:   9 years ago
How, (7/60 * 4) = 7/15?

Guna said:   11 months ago
Agree, the answer is D.
(6)

Yusuf said:   4 years ago
A+b 1 days work =7/60.
(2)

Deepak said:   1 decade ago
Why are using 1-7/15?


Post your comments here:

Your comments will be displayed after verification.