Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
351 comments Page 34 of 36.

Mohsin said:   1 decade ago
How (7/60*4) = 7/15?

Md Afif said:   4 years ago
How 1-7/15? Explain.
(3)

Pradeepshne said:   1 decade ago
Wow really superb.

Hashir Quraishi said:   1 decade ago
Swetha you rocked.

Shro said:   1 decade ago
Thanku Prakash :).

Esha said:   1 decade ago
How did 7/20 come?

Mounika said:   1 decade ago
Why 300 will come?

Ramkumar said:   1 decade ago
Nice work swetha.

Keshav said:   1 decade ago
Nice explanation.

Nanda said:   1 decade ago
How you got 7/15?