Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
60 | 15 |
Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
15 | 15 |
Discussion:
344 comments Page 34 of 35.
Esha said:
1 decade ago
How did 7/20 come?
Mounika said:
1 decade ago
Why 300 will come?
Ramkumar said:
1 decade ago
Nice work swetha.
Keshav said:
10 years ago
Nice explanation.
Nanda said:
9 years ago
How you got 7/15?
Jagannath naik said:
7 years ago
How to find 1/15?
Ni333 said:
1 decade ago
Thanks analyser.
Poorni said:
1 decade ago
Why (1 - 7/15)?
/mat said:
1 decade ago
Why 1/15, 1/20?
Vivek said:
9 years ago
How 7/60 came?
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers