A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 34 of 35.

Esha said:   1 decade ago
How did 7/20 come?

Mounika said:   1 decade ago
Why 300 will come?

Ramkumar said:   1 decade ago
Nice work swetha.

Keshav said:   10 years ago
Nice explanation.

Nanda said:   9 years ago
How you got 7/15?

Jagannath naik said:   7 years ago
How to find 1/15?

Ni333 said:   1 decade ago
Thanks analyser.

Poorni said:   1 decade ago
Why (1 - 7/15)?

/mat said:   1 decade ago
Why 1/15, 1/20?

Vivek said:   9 years ago
How 7/60 came?


Post your comments here:

Your comments will be displayed after verification.