Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 32 of 35.

Sheelu said:   1 decade ago
1/15+1/20=7/60
7/60*4=8/15

Sunil jat kantia said:   1 decade ago
Please solve this problem.

Pooja said:   8 years ago
Why we subtract 7/15 by 1?

Sajid said:   6 months ago
(+1-7/15).
(-*-=+) = 8/15.
(3)

Beer ibrahim said:   1 decade ago
Why (1-7/15) is applied ?
(1)

Asshok said:   9 years ago
Why 1 - 7/15? Explain it.

Sagar said:   8 years ago
How to 300 come? Explain.

Gowtham said:   1 decade ago
How came remaining days?

Santhi said:   1 decade ago
Good explanation swetha.

Aadesh said:   8 years ago
28/60=14/30=7/15 @Pooja.