Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 11 of 35.

Arpit kashyap said:   1 decade ago
A's 1 day's work = 1/15,

B's 1 day's work = 1/20,

Since they work together for 4 days so that their left work in fraction = [1 - (1/15 + 1/20)]*4.

= (8/60)*4.

= 8/15.

Ashwini said:   10 years ago
Its very simple 1/1-7/15.

LCM between 1 and 15 is 15.

So = (1/1)*(15/15) - (7/15)*(1/1) {Make both the denominator as 15 i.e LCM}.

= 15/15 - 7/15.

= (15-7)/15 = 8/15.

Hope understood!

ANURAG SAXENA said:   1 decade ago
LCM - 15, 20.
LCM = 60 UNIT.

A-- 15 DAY -60/15 = 4 U/D
B -- 20 DAY -60/20 = 3 U/D

A+B = 7 U/D.

4 DAYS = 7x4 = 28 U.

REAMING UNIT = 60-28 = 32 UNIT.
REAMING WORK = 32/60 = 8/15 DAYS.

Sundar said:   1 decade ago
@Poorni:

The total work = 1;

Work done by A and B in 4 days = 7/15.

Therefore, the pending work = 1 - 7/15 = 0.533333333... (or) 8/15.

Hope this help you. Have a nice day!
(1)

Analyser said:   1 decade ago
Since work done is 7/15....which is 7 parts out of 15.....

So obviously total work wud be 15/15......which is 1....

Hence we subtract 7/15...from 15/15 or 1..... i.e 1-7/15.

Pankaj Kushwah said:   1 month ago
The answer is 8/15.
Lcm of 15 and 20.
Then it will give you 60.
Now 60/15 = 4, 60/20 = 3.
Together for one day 4 + 3 = 7.
For 4 days = 4 * 7 = 28.
60 - 28 = 32.
32/60 = 8/15.
(50)

Debasis Das said:   10 years ago
A's 1 day work = 1/15.

B's 1 day work = 1/20.

Hence, A+B 1 day work = (1/15+1/20) = 7/60.

So, A+B 4 day work = (7/60*4) = 7/15.

Then, remaining work = 1-7/15 = 8/15.

Anjali thakur said:   3 months ago
The answer is 8/15.
Lcm of 15 and 20.
Then it will give you 60.
Now 60/15 = 4, 60/20 = 3.
Together for one day 4 + 3=7.
For 4 days = 4 * 7=28.
60-28 = 32.
32/60 = 8/15.
(49)

Anand said:   1 decade ago
Balance work = 8/15.

A = 1/15, B = 1/20.

Total no of days required to complete remaining work.

A = (8/15) / (1/15) = 8 days,

B = (8/15) / (1/20) = 10 2/3 days.

Srikanth said:   1 decade ago
In all these problems total work taken as "1" so we have to remove the resulting answer i.e., 7/15 from total work"1" so remaining work is (1-7/15) i.e., 8/15.


Post your comments here:

Your comments will be displayed after verification.