Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
355 comments Page 12 of 36.

Anjali thakur said:   1 year ago
The answer is 8/15.
Lcm of 15 and 20.
Then it will give you 60.
Now 60/15 = 4, 60/20 = 3.
Together for one day 4 + 3=7.
For 4 days = 4 * 7=28.
60-28 = 32.
32/60 = 8/15.
(71)

Anand said:   1 decade ago
Balance work = 8/15.

A = 1/15, B = 1/20.

Total no of days required to complete remaining work.

A = (8/15) / (1/15) = 8 days,

B = (8/15) / (1/20) = 10 2/3 days.

Ambika said:   2 months ago
A ---> 15 days.
B ---> 20 days.
LCM --> 60.

A--> efficiency 4.
B--> efficiency 3.

Total 4 days work = 4 * 7 = 28.
Remaining work = 60 - 28 = 32.
32/60 = 8/15.
(29)

Srikanth said:   1 decade ago
In all these problems total work taken as "1" so we have to remove the resulting answer i.e., 7/15 from total work"1" so remaining work is (1-7/15) i.e., 8/15.

PriyA said:   1 decade ago
But still I can't understand the logic behind the subtraction of 1. I have read @Mangesh answer. But why do we assume "one"? They did't mention anything right?

Virat said:   6 years ago
A=15 Days.
B=20 Days.

LCM 60.
A's 1 Day work=4.
B's 1 Day work=3.

Both together 1 Day work= 7/60.
Both together 4 Days work= 28/60.

Rest work= 32/60 = 8/15.

Malik shahnawaz said:   4 months ago
W(A) = eff * time = 4 * 4 = 16
W(B) = rff * time = 3 * 4 = 12.
Total work in 4 days = 28.
Remaining work = 60 - 28 = 32.
Fraction of work left = 32/60 = 8/15.
(30)

Meena said:   1 decade ago
Fraction of work done in 4 days = 7/15.
(It means that out of 15 parts, 7 parts has been done. So 8 parts left)

Therefore, the fraction of work left = 8/15.

Prabhu said:   9 years ago
Can anyone solve this?

Problem: 'A' can do a piece of in 6days, 'B' in 9days and 'C' in 12 days. In how many days will all of the together finish the work?

VisHnu RaM said:   4 years ago
Thank you for giving the clear explanation @Swetha.

And 60 will come, No of days LCM

15 days to 15 * 4 = 60.
20 days to 20 * 3 = 60.

So, the LCM is 60.
(13)


Post your comments here:

Your comments will be displayed after verification.