Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 10 of 35.

Naren said:   10 years ago
Dear friends, I have the doubt that why we take the total work as 1 instead of taking 60.

We take LCM of 15 & 20 as 60. So we consider 60 units as the total work. So we should take 60? Help me please.

Kennethy said:   9 years ago
@ Vishwanath.

7/60 * 4 = 7/15.
This is how;
It's like multiplying 7/60 by 4/1 = 7 * 4/60 * 1
This gives us 28/60.
We get a common divisor of the numerator and denominator which is 4.

Hence it is 7/15.

Rahul Manjhi said:   8 years ago
If A can do work in 15days then in 4days will be=4/15,
Similarly, if B can do work in 20days then 4days will be=4/20=1/5,
Therefore adding A and b together=4/15+1/5=7/15,
Now remaining work=1-7/15=8/15.

Mogarg said:   7 years ago
@All

Here is the Concept of 1.

If a can do work in 5 days, then,
In one day = 1/5.
In 5 days = 1/5+1/5+1/5+1/5+1/5.
= 5/5 =1.
the concept of 1 means total work, not a day so assume our total work 1.

Sravanthi tolusuri said:   6 months ago
LCM of 15,20 = 60
days * efficiency = work so, 15 * 4 = 60 20 * 3 = 60.
Efficiencies are 4+3 =7,
They worked for 4 days 7*4 =28.
Total work =60,
60 - 28 =32.
Then the remaining work = 32/60 = 8/15.
(116)

Vishnu said:   12 months ago
A->15.
B->20.
LCM of 15,20 is 60.
A can do 4 parts and B can do 3 parts.
A and B together complete 7 parts in 1 day.
for 4 days 28 parts can complete.
60-28 = 32(leftover work).
32/60 = 8/15.
(268)

Sweety said:   1 decade ago
A's 1 day's work = 1/15.

B's 1 day's work = 1/20.

(A + B) 's 1 day's work = (1+1) = 7.

15 20 60.

(A + B) 's 4 day's work = (7x1) = 7.

60 4 15.

Therefore, Remaining work = (1+7) = 8.

15 15.

Mitsuna said:   10 years ago
"From the above answer, we can say 15/8 days required to.

Complete the remaining work by A and B".

Can you please calculate this in whole number so that we can assume the exact days remaining?

Giri said:   2 years ago
Just take LCM on 15 and 20 of 60.
Total work 60.

Capacity A 4 and capacity B 3 total 7.
They both worked together for 4 days and completed work 28.
Remaining work 32/60,
So, the Answer 8/15.
(60)

Urmm said:   1 decade ago
L.C.M. of 15 & 20 are 60
and 60/15=4
and 60/20=3
so 4+3=7 as numerator
and 60 is denominator
OR
1/15+1/20=[(1*20)+(1*15)]/300=(20+15)/300=35/300=7/60
35 devide by 5 and 300 devide by 5


Post your comments here:

Your comments will be displayed after verification.