Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 9 of 35.

SUNDARA said:   8 years ago
A & B together requires 1/15+1/20=7/60 or 60/7days =8 4/7 days to complete the work.

After 4 days work, pending work is 8 4/7 -4=4 4/7days work.

= 4 4/7 divide by 8 4/7=32/7 divide 60/7=32/60=8/15 work pending.

Tinu said:   1 decade ago
Because a work is calculated as 1.

If any value coming under fraction it comes between 0 to 1 so only.

Like 15/15 = 1.

Likewise Here we have 7/15 only, we need to know the remaining.

15/15-7/15 = 15-7/15 = 8/15.

Er.Ketan Patel said:   1 decade ago
Take LCM is 60 mean total work done is 60.

It mean "a" can do 4 unit/day, "b" can do 3 unit/day.

Total 3+4 = 7/60.

Both do work together 4 days mean (7*4=28).

They complete the work 28 (60-28=32).

32/60 = 8/15.

Swetha said:   6 years ago
We know A done his work in 15 days and B in 20 days so total work is we take as 1.work is inversely proportion to days 1÷15 +1÷20=(15+20)/15x20=35/300=7/60=7x4/60=28/60=1-28/60=8/15.

Here 1 indicates total work.

Aravind said:   1 decade ago
We have to divide the denominator by its common divisible number and cross multiply it in numerator so you will get 7 then mutilply the highest remainder of lcm with the lowest denominator. You will get answer.

Jinto said:   10 years ago
(A+B) 's 1 day's work = 7/60.

So (A+B) can finish the work in 60/7 day.

(A+B) 's 4 day's work = 7/15.

So remaining work = (60/7) - (7/15).

Is this correct? Why remaining work = (1-7/15), from where 1 came?

Jigme wangchuk said:   4 years ago
Simple method.
A = 15 days,
B = 20 days,
No days of work together (A+B) = 4 days,
Fraction of work = 4* sum/product.
= 4*(15+20/15*20) =140/300 simplify = 7/15.
Now, remaining fraction of work = 1-7/15
= 8/15.

Mallarapusudhakar said:   1 decade ago
a = 15, b = 20, together c = 4 but LCM of in this 3 numbers is 60.

So a is 15(4), b is 20(3) and c is 4(15).

The first of 2 function is (4+3) remaining c(15).

The total of LCM(60).

15-7 = 8.

8/60 answer.

Mounika said:   1 decade ago
'1' is the total work that has to be done. (It has to be taken by default in time and work).

7/15 is (A+B) 4 day's work.

So, total work- (A+B) 's 4 day's work=work that is left to be done.

1-7/15 = 8/15.

Indu said:   1 decade ago
Short trick if you are use to of percentage:

A's 1 day's work = 6.67% (100/15).
B's 1 day's work = 5%.

A+B's 1 day's work = 11.67%.
A+B's 4 day's work = 46.68%.

Remaining... 100-46.68 = 53.33% i.e. 8/15.


Post your comments here:

Your comments will be displayed after verification.