A and B can do a job together in 7 days. A is 13/4 times as efficient as B. The same job can be done by A alone in :

9 1 days
3

11 days

12 1 days
4

16 1 days
3

Answer: Option
Explanation:

(A's 1 day's work) : (B's 1 day's work) = 7 : 1   =   7 : 4.
4

Let A's and B's 1 day's work be 7x and 4x respectively.

Then, 7x + 4x = 1     =>     11x = 1     =>     x = 1 .
7 7 77

Therefore A's 1 day's work = ( 1 x 7 ) = 1 .
77 11

Discussion:
53 comments Page 4 of 6.

M.vignesh said:   1 decade ago
A=7/4
B=1
A:B=7/4:1
So A:b=7:4
Total Working Days=7*4=28
a=28/7=4
b=28/4=7
a=a+b
a=4+7=11
A alone=11

Divya said:   1 decade ago
Because a is 7/4 times efficient than b => a= 7/4b

a:b= 7/4b:b (b's get cancelled.)

=> 7/4:1

Kirshna said:   1 decade ago
How get a:b :: 7/4:1 ?

Vembarasi pandiyan said:   1 decade ago
Here efficiency is given so we have to change efficiency into time but in this this why the efficiency is not change I want to know the reason please explain it. 7/4:1=7x:4x this is efficiency 4x:7x this is the time in this question why we are not change the efficiency into time.

SHIVAM RANA said:   1 decade ago
As A = 7/4B-------(1).

=> A+B GIVES WORK DONE IN 7 DAYS.
=> Unity gives that work in 7*(A+B) DAYS.

=> Using (1).
=> A gives that work in (7*(A+4/7A))/A DAYS.
=> 11 DAYS.

Chara said:   1 decade ago
A's working capacity = X.
B's working capacity = Y.

Given, X + Y = 1/30 ................equation(1).

Also, X = 7/4 Y

i.e.. Y= 4/7 X .................equation (2).

PUTTING Y=4/7X from eqtn (2) in Eqtn(1), we get,

X= 1/11.

i.e.. A working capacity is 1/11( interpretation: "A" can do 1 work in 11 days).

Divi said:   1 decade ago
A is 7/4 efficient than B means A=7/4B =>B=4/7A.

A and B together can complete the work in 7 days.
[i.e.Time is directly proportional to work => 7days=work => 1 day=1/7th work].

So,

A + B = 1/7.
A + 4/7A= 1/7.
11/7A = 1/7.
A = 1/11.

Hence, A alone can work for 11 days.

Pari said:   1 decade ago
GIVEN : A=7/4B, THEREFORE B = 4/7A.

A + B = 1/7.
A + 4/7A = 1/7.
11/7A = 1/7.
A = I/7*7/11 = 1/11.

Hence 11 days.
Hope this is a correct way.

Raj said:   1 decade ago
How we get A =7/4? Please help me.

Iovd said:   1 decade ago
@Raj.

They given 1*3/4 in example after solving it we get 7/4(4*1+3).