29.
A and B can do a job together in 7 days. A is 13/4 times as efficient as B. The same job can be done by A alone in :

9 1 days
3

11 days

12 1 days
4

16 1 days
3

Answer: Option
Explanation:

(A's 1 day's work) : (B's 1 day's work) = 7 : 1   =   7 : 4.
4

Let A's and B's 1 day's work be 7x and 4x respectively.

Then, 7x + 4x = 1     =>     11x = 1     =>     x = 1 .
7 7 77

Therefore A's 1 day's work = ( 1 x 7 ) = 1 .
77 11

Discussion:
54 comments Page 3 of 6.

Anil kumar reddy said:   10 years ago
a + b = 7 days.
a = 7/4 * b.
Therefore a + 4/7a - 7 days {since men is inversely proportional to days}.

11a/7 - 7 days for getting a divide with 11/7 and another side multiply with 11/7 then we get 11 days to get complete by alone.

Vaibhav jain said:   10 years ago
Let,

A = x.
B = 7/4x.
Total work = 7x (i.e. Lcm of A &B).
A's one day work = 7.
B's one day work = 4.
(A + B)'s one day work = 11.
As we know that total work we have 7x.
Using formula of work --->(total work/(A+B) one day work) = (A+B) total work.
7x/11 = 7--->x=7*11/7--> x = 11 i.e total days of x.

Bharathi said:   9 years ago
It's easy to understand. Thanks @Kuntal.

Adithya vinay kumar said:   1 decade ago
How come efficiency is directly proportional to the no of days worked?

Swapna said:   9 years ago
7+4=11......28 ,7....? 11/7*28 = 44 ans.

Padma said:   9 years ago
Why have they taken efficiency as such without converting it to number of days?

Prabhu said:   9 years ago
Nice explanation @Jimmy John.

Mohan said:   2 days ago
A and B can do a job together in 7 days.
A is 1⅓ times as efficient as B.

Efficiency ratio:
A : B = 4 : 3.

Total efficiency:
4 + 3 = 7 units/day.

Since they complete the work in 7 days:

Total work = 7 × 7 = 49 units.
A's efficiency = 4 units/day.

Time taken by A alone:

Time = Total Work ÷ A's Efficiency
Time = 49 ÷ 4.
Time = 12¼ days.
Answer: 12¼ days.

SHIVAM RANA said:   1 decade ago
As A = 7/4B-------(1).

=> A+B GIVES WORK DONE IN 7 DAYS.
=> Unity gives that work in 7*(A+B) DAYS.

=> Using (1).
=> A gives that work in (7*(A+4/7A))/A DAYS.
=> 11 DAYS.

Kirshna said:   2 decades ago
How get a:b :: 7/4:1 ?