24.
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
4 days
6 days
8 days
18 days
Answer: Option
Explanation:

Ratio of rates of working of A and B = 2 : 1.

So, ratio of times taken = 1 : 2.

B's 1 day's work = 1 .
12

Therefore A's 1 day's work = 1 ; (2 times of B's work)
6

(A + B)'s 1 day's work = ( 1 + 1 ) = 3 = 1 .
6 12 12 4

So, A and B together can finish the work in 4 days.

Discussion:
28 comments Page 3 of 3.

Atul1487 said:   1 decade ago
Simple method without any rubbish ratio.
Suppose B completes 1 work in x days.

So B completed work in 1 day = 1/x.............1.

Now A completes 1 work = x/2 (Cz A is twice faster than B).

So A completed work in 1 day = 2/x.............2.

Together their Work = 1/x + 2 /x.
Given x = 12.

So,
Together their Work = 1/12 + 2 /12.

== 1/12 + 1/6.
==1/4 or 4 days.

No ratio - nothing complicated.

Omkar said:   1 decade ago
A = 2B.

Hence,

A+B = 2B + B

i.e. as good as three Bs working together.

B completes in 12 Days,

3B will take 1/3rd of the time i.e. 12/3 = 4.

Kapil said:   1 decade ago
Simple : A 's twice ie Half of B. . .So B is 1/12 thn Frm tis A is 1/12. . .thn A+B we get t Ans. . .

Deepa said:   1 decade ago
B'S one day work=1/12
A'S one day work=2(1/12)=1/6
(A+B) one day work=(1/12)+(1/6)=1/4
hence A and B together complete the work in 4 days

Umeshprasad said:   1 decade ago
Let A's 1 day work is x
B's 1 day work is 1/12
from question a is twice as fast as B
so A=2B------------(1)
x=2*1/12=>1/6
which is one day work of A
combine one day work of A and B is (1/6)+(1/12)
which will give u 1/4
so the entire work they will finish in 4 day.

Arun Pandian said:   1 decade ago
SHORT CUT METHOD:
let x=2(bcz A is twice as fast as B)
n=12(bcz B completes the work in 12 days)
use the formula:A&B together do the work in p days as follows
p=n/x+1
=12/3
=4days

Ghousia said:   1 decade ago
simplest method:
A is twice of B then B=2A
B completes work in=12
then 2A=12=>A=6
A's 1 day work=1/6, B's 1 day work=1/12
(A+B)'s 1 day work=(1/6+1/12)=3/12=1/4
now (A+B) together finish work in 4days

Paandu said:   1 decade ago
Why we are ratio this problem and ratio of times taken = 1:2 ?


Post your comments here: