Discussion Forum : Time and Work - General Questions (Q.No. 2)
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

9 1 days
5

9 2 days
5

9 3 days
5

10
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ,
4

A's 1 day's work = 1 ,
16

B's 1 day's work = 1 .
12

Therefore C's 1 day's work = 1 - ( 1 + 1 ) = ( 1 - 7 ) = 5 .
4 16 12 4 48 48

So, C alone can do the work in 48 = 9 3 days.
5 5

Discussion:
224 comments Page 9 of 23.

Siva Ranjini said:   2 years ago
A = 48/16=3w/d
B = 48/12=4w/d
C = ?
Total work = 48.
One day completed work = 48/4 = 12.
3+4+? = 12.
C work per day = 5w/d.
C = 48/5.
Ans = 9 3/5 days.
(96)

Shantanu said:   1 decade ago
Reema
look
A's 1 day's work = 1/16
because he took 16 days to complete the task

similarly
C's 1 day's work =5/48
so total no. of days will be 48/5

Jagan said:   1 decade ago
@ Uthappa

1/4-7/48 = ((48*1)-(7*4))/(4*48) //cross multiplication

=(48-28)/192 = 20/192 //ok........ now its divisible by 4

=5/48 // r u got it?

Shivam sharma said:   8 years ago
Help here, let's take c's work to be X then (1/16 + 1/12 + 1/X) = 1 but when I find for X by multiplying 4 inside of the bracket. I get a 80/11.

Lijin said:   10 years ago
How it possible to write 5/48 to 48/5?

See A can complete a work in n days.

A's 1 day work = 1/n.

So here 1/n = 5/48.

So n = 48/5.

Got it!

Jack said:   1 decade ago
B's 1 day's work = 1/12.

Therefore C's 1 day's work = 1-(1+1) = (1 -7) = 5.

4 16 12 4 48 48.

So, C alone can do the work in 48 = 93 days.

Sankalp said:   9 years ago
Hi, I have a doubt. Please clarify it.

After finding LCM why do we reverse the answer? (i.e why do we have 48/5 after getting LCM as 5/48).

Prachi said:   10 years ago
Like a b c are doing work in four days then can we assume the approach like it.

1/16 + 1/12+x = 4.

So x = 41/48, work of c.

Please tell.

Sona said:   1 decade ago
Hey I understood they gave answer in fraction form so 5/48 we need not any fraction so its inverse 48/5.

C = 1/4 = 5/48.

C = 4 = 48/5.

Arun kumar arui said:   1 decade ago
A+B+C = 1/4.
1/16+1/12+1/x = 1/4.
(1/16+1/12-1/4) = -1/x.

Taking lcm.
-5/48 = -1/x.

cross multiplying,
-5x = -48.
x = 48/5.
x = 9 3/5.