Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 2)
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

9 1 days
5

9 2 days
5

9 3 days
5

10
Answer: Option
Explanation:

(A + B + C)'s 1 day's work = 1 ,
4

A's 1 day's work = 1 ,
16

B's 1 day's work = 1 .
12

Therefore C's 1 day's work = 1 - ( 1 + 1 ) = ( 1 - 7 ) = 5 .
4 16 12 4 48 48

So, C alone can do the work in 48 = 9 3 days.
5 5

Discussion:
224 comments Page 17 of 23.

Pavani said:   7 years ago
(A+B+C)'s efficiency - (A+B)'s efficiency = C's efficiency.
(1/4) - (1/16+1/12) = C's efficiency.
5/48 = C's efficiency.
So, the time taken, to complete the total work, by C = 48/5= 9 3/5.

Justine said:   7 years ago
How come that 48 gets retain? when you cross multiply 48/1 * 1/16 = 3 and 48/1 * 1/12 = 4?

Please explain me.

Imran said:   7 years ago
Can anyone explain me this question by LCM method?

TRUPTIMAYEE BAHINIPATI said:   7 years ago
The solution in LCM method is;

Solution :
SUPPOSE TOTAL WORK=1UNIT.
A=15d L.C.M. of 15,20=60.
B=20d.
Then A=4.
B=3.
A+B=7unit=60.
4 unit=60/7*1/4=15/7day.
1day work of A+B=7/15unit.
Remaining work=1-7/15=8/15 unit left (Ans.)

Siba siddquie said:   7 years ago
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:


LCm of A,B,A+B+C (16,12,4)=total work=48...;;
A' 1 day work=48/16=3;
same B=48/12=4..A+B+C=48/4=12,
A+B+C=12,
3+4+C=12,
C 'one day work =5,
total work is =48.

C completes the work in (days) = total work/one day work..(formula) = 48/5=9(3/5) => answer.

Jaga said:   7 years ago
Thanks @Aanurag.

Pooja said:   7 years ago
As per formula: If A completes 1/n work in 1 day then the days required by him to complete that 1 work alone will be 1 ÷ 1/n = n days.

Similarly, C can complete 5/48 part of the work in a day. To complete 1 work alone he will take 1 ÷ 5/48 days to 48/5.

Suchi said:   7 years ago
Thank you @Siba.

Aruva said:   7 years ago
Thank you @Soujanya.

Sunshine said:   7 years ago
A work = 16 days.
B work = 12 days.

Total work was done by A and B = 48 unit (LCM Of A and B).

So work done by A in one day = 48/16= 3 unit.
And work was done by B in one day = 48/12 = 4 unit.

So work done by A and B in 1 day = 3+4 = 7 unit.
Work was done by A and B in 4 days = 7*4 = 28 unit.

So remaining work = 48-28 = 20 unit.
So work done by C in one day= 20/4 = 5 unit.

So, the total work was done by C in days = 48/5 days =9*3/5 days.


Post your comments here:

Your comments will be displayed after verification.