Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 6)
6.
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
Answer: Option
Explanation:
Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.
Then, 6x + 8y = | 1 | and 26x + 48y = | 1 | . |
10 | 2 |
Solving these two equations, we get : x = | 1 | and y = | 1 | . |
100 | 200 |
(15 men + 20 boy)'s 1 day's work = | ![]() |
15 | + | 20 | ![]() |
= | 1 | . |
100 | 200 | 4 |
15 men and 20 boys can do the work in 4 days.
Discussion:
202 comments Page 2 of 21.
Arun said:
2 years ago
From given data,
6M+8B ---> 10days.
26M+48B ---> 2days.
15M+20B ---> t days.
By using Product approach
WF1*T1=WF2*T2.
(6M+8B)*10=(26M+48B)*2,
4M=8B,
M/B=2/1,
M=2;B=1.
Now substitute We get;
20 --->10 days.
100 --->2 days.
50 ---> t days.
100*2=50*t(Product approach)
t=4 i.e.,4 days.
6M+8B ---> 10days.
26M+48B ---> 2days.
15M+20B ---> t days.
By using Product approach
WF1*T1=WF2*T2.
(6M+8B)*10=(26M+48B)*2,
4M=8B,
M/B=2/1,
M=2;B=1.
Now substitute We get;
20 --->10 days.
100 --->2 days.
50 ---> t days.
100*2=50*t(Product approach)
t=4 i.e.,4 days.
(41)
Parkavi said:
5 years ago
(6m+8b)*10 = (26m + 48b) * 2.
(6m+8b)*5= (26m + 48b),
20m+40b =26m + 48b.
4m. = 8b,
M/b = 2/1.
Now;
(6*2+8*1) * 10 = (15 * 2 + 20 * 1) * X.
12+8 ) * 10 = (30+20) * X,
200. = 50 * X.
X = 4.
(6m+8b)*5= (26m + 48b),
20m+40b =26m + 48b.
4m. = 8b,
M/b = 2/1.
Now;
(6*2+8*1) * 10 = (15 * 2 + 20 * 1) * X.
12+8 ) * 10 = (30+20) * X,
200. = 50 * X.
X = 4.
(35)
Bajrang Dangi said:
6 months ago
Given:
6M + 8B → 10 days.
26M + 48B → 2 days.
Step 1: Find the Work Ratio of M and B.
Using:
(6M+8B)×10=(26M+48B)×2.
Dividing by 2:
(6M+8B)×5 = 26M + 48B.
Rearrange:
30M + 40B = 26M + 48B
4M = 8B⇒M = 2B.
Step 2: Find Total Work in B Units;
From (6M + 8B) × 10:
(6×2B + 8B) × 10 = 200B,
Total Work = 200B.
Step 3: Find Time for 15M + 20B
Convert 15M into B units:
(15×2B + 20B) × D = 200B,
(30B + 20B)× D = 200B,
50B × D = 200B.
D = 4.
And the Final Answer: 4 days.
6M + 8B → 10 days.
26M + 48B → 2 days.
Step 1: Find the Work Ratio of M and B.
Using:
(6M+8B)×10=(26M+48B)×2.
Dividing by 2:
(6M+8B)×5 = 26M + 48B.
Rearrange:
30M + 40B = 26M + 48B
4M = 8B⇒M = 2B.
Step 2: Find Total Work in B Units;
From (6M + 8B) × 10:
(6×2B + 8B) × 10 = 200B,
Total Work = 200B.
Step 3: Find Time for 15M + 20B
Convert 15M into B units:
(15×2B + 20B) × D = 200B,
(30B + 20B)× D = 200B,
50B × D = 200B.
D = 4.
And the Final Answer: 4 days.
(22)
Sujan gautam said:
3 years ago
15/6=2.5, 20/8=2.5.
Then , 10(6m and 8b) /2.5=4.
Then , 10(6m and 8b) /2.5=4.
(19)
Shiv said:
12 months ago
To solve this problem, let's assume:
1 man can do 'm' units of work per day
1 boy can do 'b' units of work per day
Total work is 'W' units.
From the given information, we can form two equations:
Equation 1:
(6m + 8b) * 10 = W
Equation 2:
(26m + 48b) * 2 = W
Solving these equations:
From Equation 1:
60m + 80b = W
From Equation 2:
52m + 96b = W
Setting the equations equal to each other:
60m + 80b = 52m + 96b,
8m = 16b,
m = 2b.
Substituting m = 2b in Equation 1:
60(2b) + 80b = W,
120b + 80b = W,
200b = W,
Now, to find the time taken by 15 men and 20 boys:
(15m + 20b) * t = W.
Substituting m = 2b and W = 200b:
(15 * 2b + 20b) * t = 200b,
(30b + 20b) * t = 200b,
50b * t = 200b.
t = 4 days.
Therefore, 15 men and 20 boys will take 4 days to complete the work.
1 man can do 'm' units of work per day
1 boy can do 'b' units of work per day
Total work is 'W' units.
From the given information, we can form two equations:
Equation 1:
(6m + 8b) * 10 = W
Equation 2:
(26m + 48b) * 2 = W
Solving these equations:
From Equation 1:
60m + 80b = W
From Equation 2:
52m + 96b = W
Setting the equations equal to each other:
60m + 80b = 52m + 96b,
8m = 16b,
m = 2b.
Substituting m = 2b in Equation 1:
60(2b) + 80b = W,
120b + 80b = W,
200b = W,
Now, to find the time taken by 15 men and 20 boys:
(15m + 20b) * t = W.
Substituting m = 2b and W = 200b:
(15 * 2b + 20b) * t = 200b,
(30b + 20b) * t = 200b,
50b * t = 200b.
t = 4 days.
Therefore, 15 men and 20 boys will take 4 days to complete the work.
(18)
HYACINTH S BABU said:
3 years ago
1M = 2BOY.
(15B+20B) = (6M+8B) * 10,
(15M+10M) * DAYS = (6M+4M)*10.
= 4 days is the right answer.
(15B+20B) = (6M+8B) * 10,
(15M+10M) * DAYS = (6M+4M)*10.
= 4 days is the right answer.
(15)
Raza said:
5 years ago
6x+8y = 1/10----------(1)
Taking 2 common on LHS
3x+4y = 1/20,
Multiply it by 5 on both side,
15x+20y = 4.
Taking 2 common on LHS
3x+4y = 1/20,
Multiply it by 5 on both side,
15x+20y = 4.
(12)
Sajid said:
3 years ago
6M+8B *10 = 26M + 48B*2.
4M = 8B.
Ratio M&B = 2/1.
Total work = 2(6M+8B) * 10.
200.
Acc to question.
15M+20B=? ,
2(15M+20B),
50.
TIME = 200/50 = 4 Days.
4M = 8B.
Ratio M&B = 2/1.
Total work = 2(6M+8B) * 10.
200.
Acc to question.
15M+20B=? ,
2(15M+20B),
50.
TIME = 200/50 = 4 Days.
(12)
ESNALA SIDDA said:
1 month ago
2(3m+4b) = 1/10,
3m+4b = 1/20,
5(3m+5b) = ?
= 5×1/20,
= 1/4,
= 4days.
3m+4b = 1/20,
5(3m+5b) = ?
= 5×1/20,
= 1/4,
= 4days.
(12)
Parmeshwar Sharma said:
2 months ago
From both conditions, equate total work:
- (6M + 8B) × 10 = (26M + 48B) × 2.
→ 60M + 80B = 52M + 96B,
→ 8M = 16B → M = 2B.
Now convert 15 men + 20 boys into boys:
→ 15 men = 30 boys → Total = 50 boys
Total work = (6M + 8B) × 10 = (12B + 8B) × 10 = 200B,
Time = 200B ÷ 50B = 4 days.
- (6M + 8B) × 10 = (26M + 48B) × 2.
→ 60M + 80B = 52M + 96B,
→ 8M = 16B → M = 2B.
Now convert 15 men + 20 boys into boys:
→ 15 men = 30 boys → Total = 50 boys
Total work = (6M + 8B) × 10 = (12B + 8B) × 10 = 200B,
Time = 200B ÷ 50B = 4 days.
(11)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers