Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 6)
6.
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
Answer: Option
Explanation:
Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.
Then, 6x + 8y = | 1 | and 26x + 48y = | 1 | . |
10 | 2 |
Solving these two equations, we get : x = | 1 | and y = | 1 | . |
100 | 200 |
(15 men + 20 boy)'s 1 day's work = | ![]() |
15 | + | 20 | ![]() |
= | 1 | . |
100 | 200 | 4 |
15 men and 20 boys can do the work in 4 days.
Discussion:
196 comments Page 2 of 20.
Yamuna said:
2 years ago
6m + 8b = 1/10.
2(3m + 4b) =1/10.
3m + 4b = 1/20.
5(3m + 4b) = 5(1/20).
15m + 20b = 1/4.
2(3m + 4b) =1/10.
3m + 4b = 1/20.
5(3m + 4b) = 5(1/20).
15m + 20b = 1/4.
(60)
Sujan gautam said:
2 years ago
15/6=2.5, 20/8=2.5.
Then , 10(6m and 8b) /2.5=4.
Then , 10(6m and 8b) /2.5=4.
(19)
HYACINTH S BABU said:
3 years ago
1M = 2BOY.
(15B+20B) = (6M+8B) * 10,
(15M+10M) * DAYS = (6M+4M)*10.
= 4 days is the right answer.
(15B+20B) = (6M+8B) * 10,
(15M+10M) * DAYS = (6M+4M)*10.
= 4 days is the right answer.
(15)
Sajid said:
3 years ago
6M+8B *10 = 26M + 48B*2.
4M = 8B.
Ratio M&B = 2/1.
Total work = 2(6M+8B) * 10.
200.
Acc to question.
15M+20B=? ,
2(15M+20B),
50.
TIME = 200/50 = 4 Days.
4M = 8B.
Ratio M&B = 2/1.
Total work = 2(6M+8B) * 10.
200.
Acc to question.
15M+20B=? ,
2(15M+20B),
50.
TIME = 200/50 = 4 Days.
(12)
Devil said:
3 years ago
Thanks for the good explanation @Parkavi.
(1)
Waseem said:
3 years ago
Thanks for explaining this @Zoya.
(4)
Nav Raj Bhatta said:
4 years ago
Find the relation between first, second to third equation.
6M+8B=10
26M+48B=2
15M+20B=?.
Now taking first equation;
6M + 8B = 10.
60M + 80B = 1.
30M + 40B = 2.
15M + 20B = 4.
6M+8B=10
26M+48B=2
15M+20B=?.
Now taking first equation;
6M + 8B = 10.
60M + 80B = 1.
30M + 40B = 2.
15M + 20B = 4.
(65)
Kriti said:
4 years ago
6men, 8boys take 10 days.
(6men, 8boys)*5 i.e. 30men ad 40boys take 2 days to complete the work.
Let 15men, 20boys take x days.
(15men, 20boys) * 2 take (x/2)days.
hence 2 = (x/2),
x = 4.
(6men, 8boys)*5 i.e. 30men ad 40boys take 2 days to complete the work.
Let 15men, 20boys take x days.
(15men, 20boys) * 2 take (x/2)days.
hence 2 = (x/2),
x = 4.
(3)
Parkavi said:
4 years ago
(6m+8b)*10 = (26m + 48b) * 2.
(6m+8b)*5= (26m + 48b),
20m+40b =26m + 48b.
4m. = 8b,
M/b = 2/1.
Now;
(6*2+8*1) * 10 = (15 * 2 + 20 * 1) * X.
12+8 ) * 10 = (30+20) * X,
200. = 50 * X.
X = 4.
(6m+8b)*5= (26m + 48b),
20m+40b =26m + 48b.
4m. = 8b,
M/b = 2/1.
Now;
(6*2+8*1) * 10 = (15 * 2 + 20 * 1) * X.
12+8 ) * 10 = (30+20) * X,
200. = 50 * X.
X = 4.
(35)
Raza said:
4 years ago
6x+8y = 1/10----------(1)
Taking 2 common on LHS
3x+4y = 1/20,
Multiply it by 5 on both side,
15x+20y = 4.
Taking 2 common on LHS
3x+4y = 1/20,
Multiply it by 5 on both side,
15x+20y = 4.
(12)
Post your comments here: