Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 6)
6.
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
4 days
5 days
6 days
7 days
Answer: Option
Explanation:

Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.

Then, 6x + 8y = 1 and 26x + 48y = 1 .
10 2

Solving these two equations, we get : x = 1 and y = 1 .
100 200

(15 men + 20 boy)'s 1 day's work = 15 + 20 = 1 .
100 200 4

15 men and 20 boys can do the work in 4 days.

Discussion:
202 comments Page 17 of 21.

Naman said:   1 decade ago
Bhanu you are genius.

Fantastic approach.

Bhagi said:   9 years ago
Can anyone tell formula for this question?

Chandra sekhar reddy said:   8 years ago
Thank you all for explaining the solution.

Manisha said:   8 years ago
Well said. Thank you for this @Siddharth.

Bhavani said:   8 years ago
Thank you for the explanation @Siddharth.

Devil said:   4 years ago
Thanks for the good explanation @Parkavi.
(1)

Rahul said:   10 years ago
How to solve 8y = 4/100, please help me.

Nagendran Periyasamy said:   9 years ago
Can anyone explain that 1/100 and 2/200?

Jyoti said:   1 decade ago
Thanks to give various tricks by all.

Chinna said:   10 years ago
Sir please give a shortcut technique.


Post your comments here:

Your comments will be displayed after verification.