Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 25)
25.
Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?
Answer: Option
Explanation:
(20 x 16) women can complete the work in 1 day.
![]() |
1 | . |
320 |
(16 x 15) men can complete the work in 1 day.
![]() |
1 |
240 |
So, required ratio |
|
||||||
|
|||||||
= 4 : 3 (cross multiplied) |
Discussion:
59 comments Page 3 of 6.
Raj said:
1 decade ago
Its very simple. See that:
20*16 = 320. work done by women.
16*15 = 240. work done by men.
Ratio = 320/240 = 4/3. Answer.
20*16 = 320. work done by women.
16*15 = 240. work done by men.
Ratio = 320/240 = 4/3. Answer.
Nilu said:
10 years ago
As per question:
20W = 16 days and 16M = 15 days.
So W = 16/20 and M = 15/16.
So M/W = 15/20 = 3/4.
So ratio is 4:3.
20W = 16 days and 16M = 15 days.
So W = 16/20 and M = 15/16.
So M/W = 15/20 = 3/4.
So ratio is 4:3.
M.Dineshkumar said:
2 decades ago
Ok what you saying is 100% right Jananipriya. Then why we have to do cross multiple work as they given in last step.
Jananipriya.P. said:
2 decades ago
Since the ratio has been asked between man and woman which is 1/240, 1/320 per day respectively. That is it Pavan.
Pavan said:
2 decades ago
Why we take 1/240:1/320?
Why not 1/320:1/240?
It will give us reverse answer as 3:4 which is the 1st option.
Why not 1/320:1/240?
It will give us reverse answer as 3:4 which is the 1st option.
Srikanth alladi said:
10 years ago
Ratio of man and woman is asked here, but not woman and man. So the answer will be 3:4 (option A).
Shweta Swarup said:
1 decade ago
sheetal ur explanation is very very good, i really liked it.
thank u so much, u helped me a lot.
thank u so much, u helped me a lot.
Shweta Swarup said:
1 decade ago
sheetal ur explanation is very very good, i really liked it.
thank u so much, u helped me a lot.
thank u so much, u helped me a lot.
Chandana said:
8 years ago
20w can take 16 days.
If 16w-----can take 20 days,
16m can take 15 days(given).
so 20:15.
4:3.
If 16w-----can take 20 days,
16m can take 15 days(given).
so 20:15.
4:3.
Gurpreet singh said:
1 decade ago
Very simple
As per question 20Women*16=16men*15
Men:women=(16*20)/(15*16)=4:3
As per question 20Women*16=16men*15
Men:women=(16*20)/(15*16)=4:3
Post your comments here: