3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 30 of 36.

Karan Singh said:   1 decade ago
Indeed, the explanation of baskar is correct.

Tarun said:   10 years ago
Anyone explain this question with LCM method.

Britney said:   5 years ago
How did we get 6/60? Anyone explain about it.
(1)

Anbu said:   1 decade ago
How you got 6/60?

I think the answer is 12.

Sindu said:   1 decade ago
Why in the last step 3 is multiplied with 5?

Vani said:   10 years ago
In last step why did they multiplied with 3?

Shashikumar g said:   7 years ago
Nice explanation, Thanks @Shashank Tripathi.

Siddu said:   1 decade ago
Please explain how we will get 6/60 please?

Anonymous said:   1 decade ago
Why do you need to find A's work in 2 days?

Parth said:   10 years ago
What is the Mean assisted in this question?