Discussion Forum : Time and Work - General Questions (Q.No. 3)
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days
Answer: Option
Explanation:

A's 2 day's work = 1 x 2 = 1 .
20 10

(A + B + C)'s 1 day's work = 1 + 1 +1 = 6 = 1 .
20 30 60 60 10

Work done in 3 days = 1 + 1 = 1 .
10 10 5

Now, 1 work is done in 3 days.
5

Whole work will be done in (3 x 5) = 15 days.

Discussion:
357 comments Page 28 of 36.

Garima Yadav said:   1 decade ago
I haven't got it. Can anyone please help me for this?

SRINIVAS said:   9 years ago
How A's 2 day's work = 1/10? Please explain the step.

Sha said:   7 years ago
How does the last step is (3*5=15)?

How come 3 here?

Yash said:   8 years ago
Why are we multiplying by 5 for whole work? Explain.

Sangi said:   7 years ago
Why 3 is multiplied with 5 at last?

Please explain.

Vinoth said:   2 decades ago
How do you know total working day is 3 (last step).
(1)

Shreya said:   1 decade ago
I dint get how did you multiply 5*3. It was 1/5 83?

Aiswarya said:   9 years ago
How did we get that 1/10+1/10 ? Can anyone help me?

Karthikeyan said:   1 decade ago
Please explain me the lcm method for this problem.

Shubham said:   8 years ago
Please explain the last step ( 1/10 + 1/10) = 1/5.


Post your comments here: