5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
185 comments Page 8 of 19.

Bhuvana said:   9 years ago
The LCM of 6,8 and 24.Then,

24/6 = 4
24/8 = 3
24/24 = 1.

So, that the ratio becomes 4:3:1.

Malli said:   9 years ago
How 1/6, 1/8, 1/24 converted into 4 : 3 : 1?

Ahamika said:   9 years ago
I still can't understand the solution. Is there any shortcut to find the solution?

K appala naidu said:   9 years ago
A's one day work = 1/6
B's one day work= 1/8
C's one day work = 1/x

A + B + C one day work = 1/3.

1/6 + 1/8 + 1/x = 1/3.
C's one day work is 1/24.

The ratio of A : B : C is 1/6 : 1/8 : 1/24 = 4 : 3 : 1.
For 8 parts 3200 for C's 1 part 3200/8 = 400. So, the answer is 400.

Ashish said:   9 years ago
We can also use the lcm method.

Bharath said:   9 years ago
NO need of looking for ratios. Just understand the question and do logically.

A = 6days
B = 8days
C = ?
A + B + C = 3200rupees.

Now we need to find how many days would C take to complete his work.
1/6 + 1/8+ C = 1/3.
C = 1/3 - (1/6 + 1/8).
1/3 - (7/24).
1/24.

So, here we found that C can do 1/24 work in one day, now in 3 days C can do:
3 * 1/24 = 1/8.

Now 1/8 * 3200 gives us the answer.
So, 1/8 * 3200 = 400.

Nithya said:   10 years ago
Your method is good % easy, Thanks @Pradeep Koney.

Vasanth said:   10 years ago
Another solution :

By ratio their wages 4 : 3 : 1, totally 8parts

(i.e) 4 + 3 + 1 = 8. athe value of one part = 3200/8 = 400.
C part is one so the answer is 400 rupees.

Naveen said:   10 years ago
@Pradeep, your method is really superb and very easy to understand. Thank you so much.

RAJNISH JHA said:   10 years ago
Given,
A finish work in 6 days.
B finish work in 8 days.

Then C's 1 day work = 1/3 - (1/6 + 1/8) = 1/24.
Then ratio of a : b : c = 4 : 3 : 1.

Then, C share for 3 days = 3 * 1/24 * 3200 = 400-> answer.