Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
179 comments Page 6 of 18.

Sweta said:   8 years ago
Can any one help me how the first step is possible?

Nagesh said:   8 years ago
Please, Anyone can you help me?

Why we are multiplying with 24 to get the ratios of a:b:c?

Rahul Manjhi said:   8 years ago
If A do work in 6days then in 3days the amount he will get=3/6*3200=1600.
If B do work in 8days then in 3days the amount he will get=3/8*3200=800.
Therefore,1600+800(A+B)took together=2800.
Now, total amount=3200.
So the amount C will get=3200-2800=400(answer).

Vasu said:   8 years ago
Thanks for all the given explanations.

The Pope said:   8 years ago
Thanks for the given Explaination.

Vishwa said:   8 years ago
No! @Priyanka.

It's the total amount given for total work done by all 3.

Total work is 8parts, out of which c can complete only 1 part hence C can get 1/8 Part of the total amount.

i.e (1/8) *3200=400.

Priyanka said:   8 years ago
Is 3200 is wage per person per day?

Ajinkya said:   8 years ago
A's 1 days work=1/6.A worked for 3 days.
So A's income will be 3200*3/6=1600 RS.
B work for 3 days = 3/8,
B's income =3/8*3200 = 1200,
So C's income= 3200-(A+B income),
= 3200-2800,
= 400.

Kartik Choudhary said:   8 years ago
Please make me understand this.

We calculated ratio 4:3:1.
But how's the last step is done?
How we calculated C's share. Please elaborate it.

Abhishek Giri said:   8 years ago
@ALL.

3 days work.
A completes in 6 days so he should get half of Rs.3200 i.e., 1600.
B's completes in 8 days means half work in 4 days. that means he has worked 1 day less than A
3200/2 = 1600.
1600/4 (B half days work) = Rs. 400 for 1-day work.
so 1600-400 = Rs .1200 (B will get).
Remaining C.
1600+1200 = 2800.
3200-2800 = 400(C will get).