Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Answer: Option
Explanation:
C's 1 day's work = | 1 | - | ![]() |
1 | + | 1 | ![]() |
= | 1 | - | 7 | = | 1 | . |
3 | 6 | 8 | 3 | 24 | 24 |
A's wages : B's wages : C's wages = | 1 | : | 1 | : | 1 | = 4 : 3 : 1. |
6 | 8 | 24 |
![]() |
![]() |
3 x | 1 | x 3200 | ![]() |
= Rs. 400. |
24 |
Discussion:
179 comments Page 4 of 18.
Zeenat said:
6 years ago
1/6 * 24 : 1/8 * 24 :1/24 * 24 convert fraction to the whole number.
Ishan raj said:
7 years ago
How 4:3:1 came? Anyone explain me.
(1)
Praveen kumar said:
7 years ago
The sum of three numbers is 275. If the ratio between the fast and second be 3:7 and that between the second and third be 4:5 then find the second number. Can anyone solve this?
Sruthi said:
7 years ago
The total work-> 24 {LCM of days}.
A's 1day work->4,
B's 1day work->3,
with the help of C they completed the work in 3 days,
A+B+C=8 {24/3 ie, total work/no.of days to complete}.
4+3+C=8.
C=1.
Then, 3200/8=400.
C does 1unit so C gets 400.
If it does 2units 400 * 2.
A's 1day work->4,
B's 1day work->3,
with the help of C they completed the work in 3 days,
A+B+C=8 {24/3 ie, total work/no.of days to complete}.
4+3+C=8.
C=1.
Then, 3200/8=400.
C does 1unit so C gets 400.
If it does 2units 400 * 2.
(1)
Vidyasri said:
7 years ago
Thank you @Sai vinay.
Jishnu said:
7 years ago
@all.
A takes 6 days to complete the job. So a one day work is 1/6 and for 3 days it is 3/6 ie 1/2.
Similarly for B for 3 days work is 3/8 now A's share is 1/2 of 3200= 1600 B's share 3/8 of 3200=1200.
So C's share 3200--- (1600+1200) = 40.
A takes 6 days to complete the job. So a one day work is 1/6 and for 3 days it is 3/6 ie 1/2.
Similarly for B for 3 days work is 3/8 now A's share is 1/2 of 3200= 1600 B's share 3/8 of 3200=1200.
So C's share 3200--- (1600+1200) = 40.
Sunil said:
7 years ago
Option A is the right answer if you perfectly have understood the question.
Here in the question, it is given that A & B undertook to do the work for 3200 then how C can earn his wages from the first day.
Here Supposed A & B if do the work in 3 days then they will able to do - 21 work
But they did it in 3 days with the help of C.
So the method is here that;
For the first two days, A+B do - 14 work.
Then with the help of C they able to finish it in 3 days so A+B+C do last day - 10 work.
That means one-day work of C is - 3.
Then the work ratio of A+B for two days with A+B+C in one day is - 14:10 = 7:5.
Then (3200 ÷12) * 5 = 1250.
Then bye one-day work ratio of A B&C = 4:3:3.
Then (3200÷10) * 3 = 375,
Hence the answer is 375.
Here in the question, it is given that A & B undertook to do the work for 3200 then how C can earn his wages from the first day.
Here Supposed A & B if do the work in 3 days then they will able to do - 21 work
But they did it in 3 days with the help of C.
So the method is here that;
For the first two days, A+B do - 14 work.
Then with the help of C they able to finish it in 3 days so A+B+C do last day - 10 work.
That means one-day work of C is - 3.
Then the work ratio of A+B for two days with A+B+C in one day is - 14:10 = 7:5.
Then (3200 ÷12) * 5 = 1250.
Then bye one-day work ratio of A B&C = 4:3:3.
Then (3200÷10) * 3 = 375,
Hence the answer is 375.
Lalit said:
7 years ago
Why we need to multiply 3200*1/8?
Taran said:
7 years ago
@All.
It is simple by solving this way.
Work = efficiency*time ----> 1
Efficiency = work/time. ----> 2
Time = work/efficiency ----> 3
Acc to question;
A can do work in 6 days.
B can do work in 8 days.
(A+B+C) Can do work in 3 days.
Taking LCM of 6,8,3 is 24.
Hence Let Work =24 units.
Now efficiency of A=24/6= 4units/day ----> using(2)
Efficiency of B=24/8= 3 units/day ----> using(2)
Efficiencyof (A+B+C) = 24/3=8unit/day ----> using(2)
Hence efficiency of C=Efficiency of (A+B+C)-Efficiency of A -Efficiency of B= 8-4-3=1unit/day.
Now we know A:B:C::4:3:1.
Let x be the price for 1 unit of work.
SO 4x+3x+x=3200.
8x=3200.
X=3200/8 =400.
As we know C can do 1unit/day.
Hence wages for C =1x(and x=400).
Hence it's 400.
It is simple by solving this way.
Work = efficiency*time ----> 1
Efficiency = work/time. ----> 2
Time = work/efficiency ----> 3
Acc to question;
A can do work in 6 days.
B can do work in 8 days.
(A+B+C) Can do work in 3 days.
Taking LCM of 6,8,3 is 24.
Hence Let Work =24 units.
Now efficiency of A=24/6= 4units/day ----> using(2)
Efficiency of B=24/8= 3 units/day ----> using(2)
Efficiencyof (A+B+C) = 24/3=8unit/day ----> using(2)
Hence efficiency of C=Efficiency of (A+B+C)-Efficiency of A -Efficiency of B= 8-4-3=1unit/day.
Now we know A:B:C::4:3:1.
Let x be the price for 1 unit of work.
SO 4x+3x+x=3200.
8x=3200.
X=3200/8 =400.
As we know C can do 1unit/day.
Hence wages for C =1x(and x=400).
Hence it's 400.
(1)
Lithi said:
7 years ago
LCM 24.
A4
B3
ABC 8
So, c=1.
3200*1/8=400.
A4
B3
ABC 8
So, c=1.
3200*1/8=400.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers