Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
179 comments Page 2 of 18.

Guna said:   1 decade ago
@Vinita

Its simple L.C.M
24-21/24*3=3/72=1/24...

SIDDHARTH said:   1 decade ago
IN 3*1/24*3200...FROM WHERE 3 IS COME

Sahil Kapoor said:   1 decade ago
I agree with siddharth, either the 3 should be removed or they should mention that A,B,C charge Rs 3200 "PER DAY"

Aatif said:   1 decade ago
1/24 is the work done by C in one day. For three days "3" is used.

Jagjeet said:   1 decade ago
I agree in question they should mention 3200 per day.

Shashank A said:   1 decade ago
The last step of calculating 3*1/24*3200 is wrong as C would alone earn 3200 that way at the end of 24 days..:).The idea should be 1 part of 8 parts earned amongst A ,B and C is earned by C.Hence its 400....

Vandhanasuberwal said:   1 decade ago
We can solve it as 1/8 multiply 3200.

Jeevana said:   1 decade ago
Can anyone help me with the first step?
why do like that only

Krishna said:   1 decade ago
See jeevana ,

a,b,c can complete work in 3 days
so a,b,c can complete a work in 1 days=1/3...........(1)
a and b can complete work in 1 day=1/6+1/8=7/24works.....(2)

c's one day works =a's and b's one day works is subtracted from a b c one days work that is(1-2)

So 1/24 works done by c
c 's 3 days work is 3/24=1/8
so c's share is = 3200/8=400

Anil said:   1 decade ago
Wages is necessary for this question ?