5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
179 comments Page 12 of 18.

Yaamu said:   6 years ago
Why we are taking ratio 3 * 3200 * 1/24 where does this 3 come from can anyone explain me?
(2)

Bijay Ghosh said:   4 years ago
We can even do it like;

C's share for 3 days = (1/(4+3+1) * 3200),
= 1/8 * 3200,
= 400.
(10)

Shyam said:   1 decade ago
It is simple, A's share is (4/8)*3200

B's share is (3/8)*3200

C's share is (1/8)*3200

Naveen said:   9 years ago
@Pradeep, your method is really superb and very easy to understand. Thank you so much.

Ahamika said:   9 years ago
I still can't understand the solution. Is there any shortcut to find the solution?

Karan k said:   3 years ago
A+B = 1/6+1/8 = 7/24.

7/24*3 = 7/8.
REMAINING WORK---> 1/8.

1/8 * 3200 = 400 rs.
(148)

Raj Pathak said:   10 years ago
Hope this will change. A, B and C total 3200 not like A and B as mentioned above.

Satyakrishna said:   1 decade ago
Is there any shortcut method to find this, by directly substituting the values?

Sangeethavimalraj said:   1 decade ago
Total amount is 3200,
Ratio 4:3:1,

4*x+3*x+1*x = 3200.

8x = 3200.

x = 400.

Aatif said:   1 decade ago
1/24 is the work done by C in one day. For three days "3" is used.


Post your comments here: