Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
185 comments Page 12 of 19.

Tabish said:   1 decade ago
Why multiplied by 24 to the A,B,C's one day work as it is the work completed by C in one day?

Hema said:   1 decade ago
Yes, I agree that amount 3200 in the question is not clearly mentioned. Is that for per day?

Pavithra said:   1 decade ago
Can anyone say how the 1/6+1/8 comes as 7/24?

I need the clear explanation of the solution.

Bhuvana said:   9 years ago
The LCM of 6,8 and 24.Then,

24/6 = 4
24/8 = 3
24/24 = 1.

So, that the ratio becomes 4:3:1.

Nagesh said:   9 years ago
Please, Anyone can you help me?

Why we are multiplying with 24 to get the ratios of a:b:c?

Yaamu said:   7 years ago
Why we are taking ratio 3 * 3200 * 1/24 where does this 3 come from can anyone explain me?
(2)

Bijay Ghosh said:   5 years ago
We can even do it like;

C's share for 3 days = (1/(4+3+1) * 3200),
= 1/8 * 3200,
= 400.
(10)

Shyam said:   2 decades ago
It is simple, A's share is (4/8)*3200

B's share is (3/8)*3200

C's share is (1/8)*3200
(1)

Naveen said:   10 years ago
@Pradeep, your method is really superb and very easy to understand. Thank you so much.

Ahamika said:   9 years ago
I still can't understand the solution. Is there any shortcut to find the solution?


Post your comments here:

Your comments will be displayed after verification.