Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
185 comments Page 11 of 19.

Sateesh Vudum said:   1 decade ago
Find the Ratio among the A, B, C.

Add the ratios = 4:3:1 = 8.

8-32000.
1-?

= 3200/8 = 400's wages.

Archita said:   1 decade ago
A 1 day work = 1/6.

B 1 day work = 1/8.

(A + B + C) complete work in = 3 days.

A + B + C one day work = 1/3.

1/6 + 1/8 + (C one day work) = 1/3.

C one day work = 1/3 - (1/6 + 1/8) = 1/24.

Total money = 3200.

So A, B, C share in the whole money is depend on their work ratio.

A work : B work : C work = 1/6 : 1/8 : 1/24.

Or 4 : 3 : 1 (multiply 24 in each).

A share = (4/8) *3200 = 1600.

B share = (3/8) * 3200 = 1200.

C share = (1/8) *3200 = 400.

Mouni said:   1 decade ago
Hi @Danish.

In sum we have total work of a, b, c so we subtract both a and b work from total work then we will get c work that is 1/24 ok.

And then to find ratio of wages we multiply with 24 why because the LCM of a, b, c is 24. So we multiply with 24 and get ratios of all.

Danish said:   1 decade ago
How do you guys know that C's work ratio is 24? Please help.

Yuvraj said:   1 decade ago
How to find A And B share?

Ram said:   1 decade ago
I think this is a wrong question. In it the information is not given that for how many days A and B are given 3200?

Anjana S Babu said:   1 decade ago
A's 1 day work = 1/6.

B's 1 day work = 1/8.

C's 1 day work = 1/3.

We can calculate both A+B = 1/6+1/8.

= 8+6/48 = 14/48.

= 7/24.

Then C's 1 day work = 1/3-7/24.

= 24-21/72 = 3/72.

= 1/24.

Kanmani Roja said:   1 decade ago
Another method to solve this problem can be:

A's 1 day work = 1/6.

B's 1 day work = 1/8.

Both combined (1 day work) = 1/6+1/8 = 7/24 work.

Hence both together completed in = 24/7 days.

Therefore in 24/7 days = 3200 wages.

C's working days = 3-24/7 = 3/7.

Hence for 24/7 days = 3200 wages.

C's 3/7 days = x wages.

To find x:

24/7(x) = 3/7*3200.

x = 400.

C should be paid by Rs.400.

Uday said:   1 decade ago
Suppose if we want A share, then.

A/(A+B+C)*3200 = 4/(4+3+1)*3200.

= 4/8*3200.

A's share = 1600.

B's share = B/(A+B+C) = 3/(4+3+1)*3200.

= 3/8*3200.

B's share = 1200.

Similarly C's share = 400.

Therefore Sum of shares of A+B+C = 3200.

Sapna said:   1 decade ago
1/6+1/8 = 8+6/48.

= 14/48.

= 7/24.