Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 5)
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800
Answer: Option
Explanation:

C's 1 day's work = 1 - 1 + 1 = 1 - 7 = 1 .
3 6 8 3 24 24

A's wages : B's wages : C's wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24

C's share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

Discussion:
185 comments Page 10 of 19.

Seema duhan said:   1 decade ago
take LCM of A and B work, then get:

A+B=7/24.

WHERE:
A+B+C = 1/3 (given).

So 7/24+C=1/3.

C=1/24.

With the ratio you would get to know the share of A, B and C.

Now the Ratio of A:B:C =1/6:1/8:1/24 (The L.C.M Of 1/6+1/8+1/24 is 24)
A:B:C =4:3:1.

So the wages can be calculated easily (4*400:3*400:1*400) which is equal to (1600:1200:400) if we add it, it would give us the total amount if 3200.

It is simple, A's share is (4/8)*3200.
B's share is (3/8)*3200.
C's share is (1/8)*3200 (because 4+3+1=8).

Soumya said:   1 decade ago
Can we solve the problem without calculating ratio?

Vikas said:   1 decade ago
No need to calculate the ratios its just wast of time.

Prince dubey said:   1 decade ago
A, B, C can complete work in 3 days.

so A, B, C can complete a work in 1 days = 1/3...........(1).

A and B can complete work in 1 day = 1/6+1/8 = 7/24 works.....(2).

C's one day works = A's and B's one day works is subtracted from A B C one days work that is(1-2).

So 1/24 works done by C.

C 's 3 days work is 3/24 = 1/8.

So C's share is = 3200/8 = 400.

Prince dubey said:   1 decade ago
Wages ratio is not important short method is.

C work in 3 days.

A & B money = 3200.

C work ratio is 1/24 by method (1/3- (1/6+1/8) ).

Last calculation is 3*1/24*3200.

Answer is 400.

Karun said:   1 decade ago
A efficiency 16.66.

B efficiency 12.50.

So total work of A+B is 29.16 remaining 70.84.

So 70.84/3 = 24(C efficency )

Satyakrishna said:   1 decade ago
Is there any shortcut method to find this, by directly substituting the values?

Vinod Rathod said:   1 decade ago
Leave every method go for simple method.

A alone can do the work in 6 days.

B alone can do the work 8 days.

They took the work at Rs 3200 with the help of C.

Lets take a per day work of A at Rs x.

Total = 3200/6 days.

= 533.33*3 days.

A = 1599.99 = 1600.

B = 3200/8 days.

= 400 * 3 days.

B = 1200.

A+B = 1600+1200 = 2800 And left 3200 -2800 = 400.

C = 400 Answer.

Rohan said:   1 decade ago
1/6 : 1/8 : 1/24 and ratio 4:3:1.

Answer above says highest number is 24 so multiply all by 24... is that the logic?

Alby said:   1 decade ago
From the ratio itself we can calculate.

A's wages:B's wages:C's wages = 4:3:1.

Then to calculate C's wages from 3200 = 1/(4+3+1) * 3200.

= 1/8 of 3200.

= 400.


Post your comments here:

Your comments will be displayed after verification.