Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 30)
30.
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
30 days
40 days
60 days
70 days
Answer: Option
Explanation:

Let A's 1 day's work = x and B's 1 day's work = y.

Then, x + y = 1 and 16x + 44y = 1.
30

Solving these two equations, we get: x = 1 and y = 1
60 60

B's 1 day's work = 1 .
60

Hence, B alone shall finish the whole work in 60 days.

Discussion:
97 comments Page 9 of 10.

Pranav Jain said:   10 years ago
What happens if the third condition is implemented saying B and C completes work in 16 days and A works for 7 days, B for 5 and C alone completes remaining work for 13 days, then C alone can complete work in how many days, how to solve this, when another variable is involved?

Jitender said:   10 years ago
I want any short method of this question.

Rutika patel said:   10 years ago
I can't understand how we can right 16x+44y = 1.

How you get 1? What is the meaning of 1?

Neha said:   10 years ago
@Varun how you take 26.66%?

Can you explain me please?

Varun said:   1 decade ago
Total work: 44+16 = 60 days.

Now a does 26.66% work.

Therefore B does 100-26.66 = 73.34% work in 44 days.

Time in which B can complete the whole work : 100/73.34*44.

= 60 days.

Usha said:   1 decade ago
I agree with @Sunil kumar.

Why it has been calculated as x+y=1/30 instead of considering 1/x + 1/Y = 1/30.

Kindly explain, I understood the above calculations but the basic equation why it was altered that I din't got.

Ray said:   10 years ago
How can you get 1 in the equation: B = 1-16x? I don't understand.

Sunil kumar said:   1 decade ago
Why can't we take 1/x, 1/y instead of x, y as one day work?

Hetal said:   1 decade ago
Yes I also get the same answer like @Sai and @Kaustubha Sen.

a+b = 1/30 (1 day's work).

So (a+b) work together for 16 days.

So, 1/30*16 = 16/30. So we get 8/15 work done together for 16 days.

Now remaining work = 1-8/15 we get 7/15.

That's why if 7/15 remaining work b takes 44 days then work done by b in 1 day.

= 1*7/44*15.

I got 94.28.

Tarik Khan said:   1 decade ago
Let total work = 1.

Work done by A is = x.

So remaining work that is done by B = 1-x.

So, total time to complete the whole work by A = 16/x....(1).

Similarly total time to complete the whole work by B = 44/(1-x).....(2).

From (1) and (2) we get.

16/x = 44/(1-x).....(3).

Solving (3) we get.

x = 4/15.

So 1-x = 11/15.

Now for B takes time 44 days to complete 11/15 work.

So total time to complete the whole work alone B = (15/11)x44 = 60 (ans).


Post your comments here:

Your comments will be displayed after verification.