Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
283 comments Page 29 of 29.

Yash Sangle said:   3 months ago
3/1 = (B)/(B-60).

As work done and time are inversely related,
So, B=90, A=30.
(1/90 + 1/30) = (2/45),
So, 22 1/5.
(2)

Mishra said:   1 month ago
Given: A takes 60 days less than B.
So, let A takes 90days,
B takes 30days.

LCM of 90, 30 = 180 and effeciency of A = 2 (180/90), B = 6 (180/30);
Both work together A + B = (2+6) = 8;
So, total work = 180(LCM);
total days = work/efficiency of both.
= 180/8 = 22.5.
(6)

Lalith kumar said:   1 month ago
First, A is thrice as good as B means.

If a takes a day to complete work, then b takes 3 days to complete the same work.

Here, time is inversely proportional to work.

So if b takes time T to complete, then a takes T/3 to complete.
In question, they mentioned that the time diff is 60 days.
So, T - T/3 = 60.
2T/3 = 60.
T = 90.
Now, calculate the combined work and how many days it will take.
1/30 + 1/90 = 2/45 = 22.5.
(2)