A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer: Option
Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
| If difference of time is 60 days, B takes | ![]() |
3 | x 60 | ![]() |
= 90 days. |
| 2 |
So, A takes 30 days to do the work.
| A's 1 day's work = | 1 |
| 30 |
| B's 1 day's work = | 1 |
| 90 |
| (A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 4 | = | 2 |
| 30 | 90 | 90 | 45 |
A and B together can do the work in |
45 | = 22 | 1 | days. |
| 2 | 2 |
Discussion:
283 comments Page 24 of 29.
Abhay said:
1 decade ago
@Neeraj-A will finish the work 60 days lesser than B,means if B takes 60 days to complete the work,A takes 1 day.
Neeraj said:
1 decade ago
A will finish the work 60 days lesser than B.
What is it mean please explain?
What is it mean please explain?
Gauarv said:
1 decade ago
Thanks harsha.
Brajesh Anuragi said:
1 decade ago
Thanks Showry for given the simple and correct ans.
Anu said:
1 decade ago
Awesome explanation HARSHA
Riyaz said:
1 decade ago
Ratio of times taken by A and B = 1 : 3.
That is If A takes 1 day B takes 3 days
Time Difference is 3-1 = 2 days
Here is the tricky part :
If A takes 1/2 day B takes 3/2 days
Time Difference is 3/2 - 1/2 = 1 days
When time difference is 60 days (Just mulitply by 60)
A takes 60/2 and B takes 3*60/2
So, A takes 30 days to do the work.
and B takes 90 days to do the work.
A's 1 day's work = 1/30
B's 1 day's work = 1/90
(A + B)'s 1 day's work = (1/30 + 1/90)= 4/90 = 2/45
A and B together can do the work in 45/2 = 22+1/2
That is If A takes 1 day B takes 3 days
Time Difference is 3-1 = 2 days
Here is the tricky part :
If A takes 1/2 day B takes 3/2 days
Time Difference is 3/2 - 1/2 = 1 days
When time difference is 60 days (Just mulitply by 60)
A takes 60/2 and B takes 3*60/2
So, A takes 30 days to do the work.
and B takes 90 days to do the work.
A's 1 day's work = 1/30
B's 1 day's work = 1/90
(A + B)'s 1 day's work = (1/30 + 1/90)= 4/90 = 2/45
A and B together can do the work in 45/2 = 22+1/2
Sundar said:
1 decade ago
If difference of time is 60 days 3*60/2 = 90 days.
I can't get this step?
Please explain.
I can't get this step?
Please explain.
Vinod reddy said:
1 decade ago
THANK U SHEETAL,your short cut method is simply super.there is no words to say
Sunil reddy said:
1 decade ago
We can use a simple formula here:[(KL)/k squqre-1)]
-->here K=3(efficiency),L=60(time) so (3*60/(3*3)-1)=>180/8=221/2
-->here K=3(efficiency),L=60(time) so (3*60/(3*3)-1)=>180/8=221/2
Pavethra said:
1 decade ago
I tell that A is thrice as good as B so it should be 3:1 na.
Am I right?
Am I right?
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers


A and B together can do the work in