Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer: Option
Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
| If difference of time is 60 days, B takes | ![]() |
3 | x 60 | ![]() |
= 90 days. |
| 2 |
So, A takes 30 days to do the work.
| A's 1 day's work = | 1 |
| 30 |
| B's 1 day's work = | 1 |
| 90 |
| (A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 4 | = | 2 |
| 30 | 90 | 90 | 45 |
A and B together can do the work in |
45 | = 22 | 1 | days. |
| 2 | 2 |
Discussion:
283 comments Page 19 of 29.
Divyanshu Dwivedi said:
1 decade ago
Simple:
A's work = x.
B's work = y = 3x.
Hence acc. to ques.: 3x - x = 60 ;.
x=30 A's.
y=90 B's.
Now.... 1/30 + 1/90 = 1/z.
z = 90/4 Answer.
A's work = x.
B's work = y = 3x.
Hence acc. to ques.: 3x - x = 60 ;.
x=30 A's.
y=90 B's.
Now.... 1/30 + 1/90 = 1/z.
z = 90/4 Answer.
Poor gamer said:
1 decade ago
Let A takes x days and B takes 60+x days.
Its given that A takes 1 days when B takes 3 days.
So,
1/3 = x/x+60.
Cross multiply and we get x = 30 i.e A.
X+60 = 30 + 60 = 90 i.e B.
Remaining as usual.
Its given that A takes 1 days when B takes 3 days.
So,
1/3 = x/x+60.
Cross multiply and we get x = 30 i.e A.
X+60 = 30 + 60 = 90 i.e B.
Remaining as usual.
Deepak Patgar said:
1 decade ago
Let A completes work in x days.
So no of days taken by B to complete the same work will be 3x days.
A takes 60 days less than B.
So 3x-60 = x.
2x = 60.
x = 30 days (number of days taken by A).
3x = 90 days (number of days taken by B).
Work done by A per day is 1/30.
Work done by B per day is 1/90.
Work done the together in 1 day will be (1/30+1/90) = 4/90.
So work done by them in 10 days will be 40/90.
Work done in 20 days 80/90.
Number of days require to do the remaining 10/90 will be 2.5 days.
Ans = 22.5 days.
So no of days taken by B to complete the same work will be 3x days.
A takes 60 days less than B.
So 3x-60 = x.
2x = 60.
x = 30 days (number of days taken by A).
3x = 90 days (number of days taken by B).
Work done by A per day is 1/30.
Work done by B per day is 1/90.
Work done the together in 1 day will be (1/30+1/90) = 4/90.
So work done by them in 10 days will be 40/90.
Work done in 20 days 80/90.
Number of days require to do the remaining 10/90 will be 2.5 days.
Ans = 22.5 days.
Piyasa Dey said:
1 decade ago
If A does a work in 1 day.
therefor B does the same work in 3 days since A is thrice as good as workman as B.
Let A completes the work in x days, B will take (x + 60) days more than A takes.
Therefore 1:3 :: x :(x + 60).
Now according to the formula if a:b :: c:d.
Then it is considered as (a * d) = (b*c).
Applying this formula we get 1*(x + 60) = 3*x.
By solving we get x= 30 i.e A takes 30 days to complete the work.
Therefore B will take (30+60)=90 days.
A's one day work = 1/30 days.
B's one day work = 1/90 days.
A+B one day work = (1/30)+(1/90) = 4/90 days.
Therefore A and B can finish the work in = 90/4.
therefor B does the same work in 3 days since A is thrice as good as workman as B.
Let A completes the work in x days, B will take (x + 60) days more than A takes.
Therefore 1:3 :: x :(x + 60).
Now according to the formula if a:b :: c:d.
Then it is considered as (a * d) = (b*c).
Applying this formula we get 1*(x + 60) = 3*x.
By solving we get x= 30 i.e A takes 30 days to complete the work.
Therefore B will take (30+60)=90 days.
A's one day work = 1/30 days.
B's one day work = 1/90 days.
A+B one day work = (1/30)+(1/90) = 4/90 days.
Therefore A and B can finish the work in = 90/4.
Kalyani said:
1 decade ago
What is the meaning of taking 3/2 in the problem. What's that ratio about?
Thaha said:
1 decade ago
"A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B."
Solution:
*********
'A' able to finish a job in 60 days 'less than B'.
Let A's work is = x days.
Let B's work is = 3x days.
A able to do a work in 60 less than B.
Therefore,
A's work = B's work - 60.
So,
x=3x-60.
Then x=30.
A can complete the work in 30 days.
B can complete the work in 3*30 = 90 days.
A's one day work = 1/30 days.
B's one day work = 1/90 days.
A+B one day work = (1/30)+(1/90) = 4/90 days.
Therefore A and B can finish the work in = 90/4.
So the answer is : Option [B].
Solution:
*********
'A' able to finish a job in 60 days 'less than B'.
Let A's work is = x days.
Let B's work is = 3x days.
A able to do a work in 60 less than B.
Therefore,
A's work = B's work - 60.
So,
x=3x-60.
Then x=30.
A can complete the work in 30 days.
B can complete the work in 3*30 = 90 days.
A's one day work = 1/30 days.
B's one day work = 1/90 days.
A+B one day work = (1/30)+(1/90) = 4/90 days.
Therefore A and B can finish the work in = 90/4.
So the answer is : Option [B].
Pranay said:
1 decade ago
The work being done by A & B is in ratio of 1:3.
This means if A does a work in 1 day, than B will do this work in 3 days.
Now let suppose this ratio is multiplied by a factor, say x.
Then ratio becomes x:3x.
Now another relation given is that A can do work 60 days faster then B. Mathematically we can write it as.
x=3x-60.
Solving this, we get x = 30.
Hence the ratio becomes 30:60.
Now we can calculate the time taken by them.
This means if A does a work in 1 day, than B will do this work in 3 days.
Now let suppose this ratio is multiplied by a factor, say x.
Then ratio becomes x:3x.
Now another relation given is that A can do work 60 days faster then B. Mathematically we can write it as.
x=3x-60.
Solving this, we get x = 30.
Hence the ratio becomes 30:60.
Now we can calculate the time taken by them.
Nithya said:
1 decade ago
Lets B takes x days to complete the Work,
Then B 's Capacity ==>1/x.
A is 3 times as good as A so A'S capacity is 3/x.
Then Time Taken by B is = x/1.
Time taken by A is = x/3.
Time difference (x-x/3)=60.
Which gives x = 90.
Time taken By B = 90.
Time taken By A = 30.
(A's Work +B's Work) 1 day Work = (1/30)+(1/90).
= 4/90.
Then Time taken to complete work is 90/4 ==> 22.5 days.
Then B 's Capacity ==>1/x.
A is 3 times as good as A so A'S capacity is 3/x.
Then Time Taken by B is = x/1.
Time taken by A is = x/3.
Time difference (x-x/3)=60.
Which gives x = 90.
Time taken By B = 90.
Time taken By A = 30.
(A's Work +B's Work) 1 day Work = (1/30)+(1/90).
= 4/90.
Then Time taken to complete work is 90/4 ==> 22.5 days.
Kumar said:
1 decade ago
How its "4/90 " ?
Poornachandran said:
1 decade ago
Guys,
I'll tell by simple method.
Given, A is thrice of B.
So A = 3B---->(1).
A's 1 day work is A=1/60--->(2).
Substitute (2) in (1),
A=3B.
We get,
3B=1/60.
B=1/180.
In question they asked A+B=how many working days?
We know A and B values.
Add A and B.
1/60+1/180=1/Work days.
Take L.C.M.
3+1/180=1/Work days.
4/180=1/work days.
1/45=1/work days.
Work days=45.
By fraction we can write 22 1/2 days.
I'll tell by simple method.
Given, A is thrice of B.
So A = 3B---->(1).
A's 1 day work is A=1/60--->(2).
Substitute (2) in (1),
A=3B.
We get,
3B=1/60.
B=1/180.
In question they asked A+B=how many working days?
We know A and B values.
Add A and B.
1/60+1/180=1/Work days.
Take L.C.M.
3+1/180=1/Work days.
4/180=1/work days.
1/45=1/work days.
Work days=45.
By fraction we can write 22 1/2 days.
Post your comments here: