Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer: Option
Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes | ![]() |
3 | x 60 | ![]() |
= 90 days. |
2 |
So, A takes 30 days to do the work.
A's 1 day's work = | 1 |
30 |
B's 1 day's work = | 1 |
90 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 4 | = | 2 |
30 | 90 | 90 | 45 |
![]() |
45 | = 22 | 1 | days. |
2 | 2 |
Discussion:
281 comments Page 18 of 29.
Sravan said:
10 years ago
Since it's mentioned that A completed 60 days less than B.
We have to know there less than rate. Since it given A is thrice as good as B.
That means it takes 1 day to A to do Bs 3 day work.
So now we can know that A can do in (3-1) = 2 days less than B.
That means A less than days for B days for 2 its 3.
Similarly for 60 less day we need to multiply 2 by 30 to get 60. Since we do on 2 (A) side we have to multiply on 3 (B) side then we get.
= 2x30 : 3x30.
We get = 60 (for A day's lesser than B) : 90 (we got B days) that means A work days = 90-60 = 30.
So 1/30 + 1/90= 0.0444 amount of work per 1 day.
For 1 piece of complete work 0.4444/0.4444 = 1/0.4444 days.
That 1 piece of work done for 22.5 days by A & B together.
We have to know there less than rate. Since it given A is thrice as good as B.
That means it takes 1 day to A to do Bs 3 day work.
So now we can know that A can do in (3-1) = 2 days less than B.
That means A less than days for B days for 2 its 3.
Similarly for 60 less day we need to multiply 2 by 30 to get 60. Since we do on 2 (A) side we have to multiply on 3 (B) side then we get.
= 2x30 : 3x30.
We get = 60 (for A day's lesser than B) : 90 (we got B days) that means A work days = 90-60 = 30.
So 1/30 + 1/90= 0.0444 amount of work per 1 day.
For 1 piece of complete work 0.4444/0.4444 = 1/0.4444 days.
That 1 piece of work done for 22.5 days by A & B together.
Bhupinder said:
10 years ago
Good explanations thanks.
Vamshidhar said:
10 years ago
In the explanation, said that,
"If difference of time is 60 days, B takes (3/2*60) = 90 days.
My opinion is if A can complete work in 60 days then B should complete work in 3*60 = 180 days but not in 90 days.
Can anyone explain this part?
"If difference of time is 60 days, B takes (3/2*60) = 90 days.
My opinion is if A can complete work in 60 days then B should complete work in 3*60 = 180 days but not in 90 days.
Can anyone explain this part?
Ram said:
9 years ago
Guys, this is pretty simple.
Given A : B = 3 : 1, difference in time taken is 2.
Let us consider it as 2 parts.
Then it's also given that A can complete the work with 60 days gap to B. Hence we can equate these 2 parts to 60 days.
Therefore 2 parts = 60 days.
A's part is 1 parts = 30 days.
B's part is 3 parts = 90 days.
Rest you know.
Hope you intelligent guys understand :).
Given A : B = 3 : 1, difference in time taken is 2.
Let us consider it as 2 parts.
Then it's also given that A can complete the work with 60 days gap to B. Hence we can equate these 2 parts to 60 days.
Therefore 2 parts = 60 days.
A's part is 1 parts = 30 days.
B's part is 3 parts = 90 days.
Rest you know.
Hope you intelligent guys understand :).
Bunny said:
9 years ago
How to do LCM?
Dipa said:
9 years ago
3x:1x
=> 3x - 1x = 60.
=> 2x = 60.
=> x = 30.
=> 3x = 90.
A+b together work = 90 * 30 / 90 + 3.
=> 2700 / 120 = 22.5 days.
=> 3x - 1x = 60.
=> 2x = 60.
=> x = 30.
=> 3x = 90.
A+b together work = 90 * 30 / 90 + 3.
=> 2700 / 120 = 22.5 days.
Pari said:
9 years ago
Thanks for giving a different solution.
Guarav said:
9 years ago
A is thrice as good as B
i.e A:B = 3:1.
The ratio will be same.
Now let a number of days for B be x.
Thus, for A it becomes (x - 60)
Now equate 3/1 = x/(x-60)(ratio of days of B to the days of A).
3x - 180 = x.
x = 180/3.
x = 90.
No of days by B is 90.
Hence days of A will be 30.
i.e A:B = 3:1.
The ratio will be same.
Now let a number of days for B be x.
Thus, for A it becomes (x - 60)
Now equate 3/1 = x/(x-60)(ratio of days of B to the days of A).
3x - 180 = x.
x = 180/3.
x = 90.
No of days by B is 90.
Hence days of A will be 30.
Ramya said:
9 years ago
Thank you @Siva.
It's simple to learn.
It's simple to learn.
Inzamamul haq said:
9 years ago
Workman.
A : B.
3 : 1.
Time taken;
A : B.
1 : 3.
A) if B finish work in 30 days then, A can finish it in 10 days. Now the difference in a day is 20.
B) if B finish work in 60 days then, A can finish it in 20 days. Now the difference in a day is 40.
C) if B finish work in 90 days then, A can finish it in 30 days. Now the difference in a day is 60.
Given question. The difference is 60 days. Hence, condition c) satisfies.
A 1-day work is 1/30.
B 1-day work is 1/90.
A + B 1 day work is 1/30 + 1/90 = 4/90.
Days to complete the work is 90/4 => 22 1/2.
A : B.
3 : 1.
Time taken;
A : B.
1 : 3.
A) if B finish work in 30 days then, A can finish it in 10 days. Now the difference in a day is 20.
B) if B finish work in 60 days then, A can finish it in 20 days. Now the difference in a day is 40.
C) if B finish work in 90 days then, A can finish it in 30 days. Now the difference in a day is 60.
Given question. The difference is 60 days. Hence, condition c) satisfies.
A 1-day work is 1/30.
B 1-day work is 1/90.
A + B 1 day work is 1/30 + 1/90 = 4/90.
Days to complete the work is 90/4 => 22 1/2.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers