Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
281 comments Page 16 of 29.

Rajat singh said:   1 decade ago
Simple solution:

a = 3b.
a-b = 60 (difference of b).

3b-b = 60.
b = 30, a = 90.

So they can together work in 1/30+1/90 = 4/90.

:->22.50.

Megala said:   1 decade ago
Please explain last 2 steps.

Surya said:   1 decade ago
Simple formula with solution:

(D) n/n2 (i.e n square)-1 = work together.

Details:

D-60, n-3, by putting the formula = (60)3/3's square-1 = 22.5 days.

Sharad said:   1 decade ago
Given A is thrice as good as B,

Therefore 3:1.

i.e 3x:x (ability to work). (Time taken is inverse of work).

Time taken by A and B to complete work = x:3x.

Difference A-B = 60.

Therefore x-3x = 60.

x = 60/2 = 30.

Now x:3x = 30:3(30).

= 30:90.

(A+B) 's 1 day = (1/30)+(1/90).

1 day = 2/45 work.

45/2 day = 1 work.

22. 5 day = 1 work.

Malleswari said:   1 decade ago
A is thrice as good as B means 3A = B.

A finish the work 60 days less than B means A = B-60.

So, 3(B-60) = B.

3B-180=B.
2B=180.
B=90.

Then,

3A=B.
3A=90.
A=30.

So, A's I day work is 1/30.
B one day work is 1/90.

Then (A+B) 1 day work together is (1/30+1/90) = 2/45.

Total days they work together is. 45/2 = 22.5.

Manju gouda said:   1 decade ago
Let us take B's work days be 'x'.

Then A's will be x/3.

Given difference is 60.

Therefore x-x/3 = 60 on solving x = 90.

Therefore B days = 90 & A = 30.

A&B together will be (90*30)/(90+30) = 22.5 days.

Lins said:   1 decade ago
1:3 = x:(x+60).

1/3 = x/(x+60).

So x+60 = 3x.

60 = 2x.

Then x = 30.

Satyawan said:   1 decade ago
The explanation given above is very difficult to understand please try to explain the concepts as simple as possible.

Naresh said:   1 decade ago
1:3.

Total 4 parts.

90/4=22.5 (one part).

Here one part means A's work. Remaining 77.5 belongs to B.

Ravi yadav said:   10 years ago
Let A takes x days and B takes y days to complete work. In one day A completed 1/x part of work and B 1/yth.

According to question 1/x = 3*1/y and y-x = 60.

By solving x=30 and y= 90.

So in one day both completed (1/x + 1/y) = 4/90.

They can do it in = 90/4 = 45/2.


Post your comments here:

Your comments will be displayed after verification.