Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
281 comments Page 10 of 29.

Dusu opo said:   8 years ago
Why 60 days? Please explain.

Vishal said:   8 years ago
I have better solution.

A:B-3:1(rate).
A:B-1:3(days).

Diff of 2 between ratio of days which is equivalent to 60 and 2*30=60.
Hence 30 will be multiplied to 1 and 3.
And we get 30 and 90.
Together days taken= 30 * 90/30 + 90 = 22 1/2.

Rizwan said:   8 years ago
From where does this 4/90 comes? How 4?

Nik said:   8 years ago
How 4/90 comes?

Pramod nepal said:   8 years ago
Let see @Shaman.

A finish work in x day and B can 5x day. Then we can do A+B= 1/x +1/5x.

We have A+B = 50,

50 = 5x/6 after sol x= 60 it means A can do in 60 min and B 300 min.

Jack said:   8 years ago
Can anyone explain me why the step 3/2*60 used. I couldn't get the logic of finding difference as 2.

Shaman said:   8 years ago
Please provide the solution of if A is 5 times better than B together they complete the work in 50 min then B alone can do the work in how many minutes.

Biplab sarkar said:   8 years ago
Here given k=3, n=60.

So formula is -> kn/ (k^2-1) =3*60/ (3^2-1) =180/8=22 1/2 days.

Rohi said:   8 years ago
Ratio of times taken by A and B = 1:3.

Means B will take 3 times which A will do in 1 time.
If difference of time is 2 days, B takes 3 days,
If the difference of time is 10 days, B takes (3/2) * 10 =15 days.

Saikrishna said:   8 years ago
a b
x 3x

2x=60 so x=30

total work=3*30=90
Ans=90/4=22 1/2.


Post your comments here:

Your comments will be displayed after verification.