Discussion Forum : Time and Work - General Questions (Q.No. 21)
21.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
4 days
6 days
8 days
12 days
Answer: Option
Explanation:

Suppose A, B and C take x, x and x days respectively to finish the work.
2 3

Then, 1 + 2 + 3 = 1
x x x 2

6 = 1
x 2

x = 12.

So, B takes (12/2) = 6 days to finish the work.

Discussion:
68 comments Page 4 of 7.

Subhasish baul said:   5 years ago
A - 12.
B - 6.
C - 4.

Work as satisfied to take together 2day finished.
Efficiency A 1 B 2 C 3.
Total work 12.
Total efficiency 6.
Finished together 12 ÷ 6 = 2day satisfied
**B alone do in 12 ÷ 2 = 6 days.

Md Ali Umar said:   1 decade ago
Hi Mini you are making equ. 2A=B & 3A=C, but so many people a making equ. A=2B & A=3C .

Which one s correct, but both one is getting same answer. I'm confussing in this prob. Pls any one describe it ?

Divya said:   1 decade ago
A=2B=3C

A+B+C=2 ----(EQ.1)

WRITING a and c in terms of b,

A=2B, C=2B/3
IN EQ.1,

2B+B+2B/3=2

3B+2B/3=2


(9B+2B)/3=2

9B+2B=2*3

11B=6

B=6/11

that means, out of 11 days, b alone completes 6 days of work.

Makvana Disha said:   9 years ago
We are also doing this,

A's 1 day work = 1/x, B's 1 day work = 2/x, C's 1 day work = 3/x.

So, (A + B + C) 's one-day work:

= (1/x + 2/x + 3/x).
= (1/x + 5x/x ^ 2).
= 1/x + 5.
= 6x/x = 6 Each of three.

Jayasree said:   1 decade ago
@nayana

Let time taken by B be x

then b= x
a = 2x which is equal to 3c
i.e 2x = 3c
c = 2x/3

so a = 2x ; b = x ; c = 2x/3

Dividing each by 2 => x , x/2 , x/3.

Hope it is clear.

Karthick M said:   3 years ago
To simple method is:
A = 2B or A=3B
(A+B)'s 1day work = 1/2=(2B+B)'s 1day work
1/2 = 3B's 1-day work
ie, B's 1 day work = 1/6
So, B's whole work done is in 6 days.
(7)

Meera said:   1 decade ago
A+B+C's 1 days work is = 1/6.

Therefore 2'days work (A+B+C) is=1/6*2=3.

B can do the work alone (2*3) =6.

So B takes 6 days to finish the work.

Is it right method? please anyone tell me.

Thameem said:   1 decade ago
here is another way of solving

given
a=2b
a=3c
a+b=1/2 (work from days)

use a's value in the equation

2b+b=1/2

then 3b=1/2
b=1/6

then b can done work alone in 6 days(days from work)

Nayana said:   1 decade ago
Hi,
Can any one exaplain why they have taken x,x/2,x/3, because in the question they have given A takes twice as much as B that means two times more than B but they are dividing it.

Manish said:   8 years ago
One day work of a,b&c=1/2
let a's one-day work=x , then b's one day work 2x & c work 3x
x+2x+3x=1/2
6x=1/2
x=1/12
b's one day work=2*1/12
=1/6

Therefore total work in 6 days.