Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 19)
19.
A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:
1 day
24
7 day
24
3 3 days
7
4 days
Answer: Option
Explanation:
Formula: If A can do a piece of work in n days, then A's 1 day's work = 1 .
n

(A + B + C)'s 1 day's work = 1 + 1 + 1 = 7 .
24 6 12 24

Formula: If A's 1 day's work = 1 , then A can finish the work in n days.
n

So, all the three together will complete the job in 24 days = 3 3 days.
7 7

Discussion:
24 comments Page 2 of 3.

Aditya said:   1 decade ago
Thank you dharma you helped me alot.

Sarthak said:   1 decade ago
Why did you ppl Reciprocal 7/24 ?

Swetha said:   1 decade ago
Given:

A can do a work in 24 days
B can do a work in 6 days
C can do a work in 12 days

Take LCM for 24,6 & 12 i.e 24
total work = 24
A's per day capacity = 24/24 = 1
B's per day capacity = 24/6 = 4
C's per day capacity = 24/12 = 2

If all working together,
their per day capacity = 1+4+2 = 7
all together will complete the work in 24/7 = 3 3/7 days

Seshapriya said:   1 decade ago
24*6 + 6*12 + 12*24 / 24*6*12 =144+72+288 / 1728

=504/1728

i.e

1728/504 days
24/7=

= 3 3/7 days option c..........

DopeBoy said:   1 decade ago
If the work done by A is n , then the work done is one day is 1/n.
Similar to (1 part of the work)/complete work.

Total work done together in one day is : 1/n = 1/12+1/24+1/6= 7/24
Total work done together : n = 24/7.
(1)

Vivek said:   1 decade ago
Hi there is a different way as well.
A 24
B 6
C 12

Now take the number that multiplies with all i.e 24.

So A 1
B 4
C 2 add all of them = 7.

Now divide 24 by 7 you will get answer = 3 3/7.

Tamanna said:   1 decade ago
Its very easy:-

A's 1 day's work = 1/24.
B's 1 day's work = 1/6.
C's 1 day's work = 1/12.

Thus, {A+B+C}'s 1 day's work = 1/24+1/6+1/12.
= 1+4+2/24[taking LCM=24].
= 7/24.

Thus, working together they will complete work in 24/7 days or 3 3/7 days.
(1)

Sanjoy said:   1 decade ago
24A = 1, 6B = 1, 12C = 1.

A = 1/24, B = 1/6 C = 1/12.

Now let us consider x day is required if all are working together.

So (A+B+C)x = 1.

(1/24+1/6+1/12)x = 1.
((1+4+2)/24)x = 1.

7/24 x = 1.
x = 24/7.
x = 3 3/7.
(3)

Narayan said:   10 years ago
LCM of 24 6 12 is 48.
(1)

Saurabh said:   9 years ago
The given answer and explanations are seems to be a right solution.


Post your comments here:

Your comments will be displayed after verification.