Discussion Forum : Time and Work - General Questions (Q.No. 19)
19.
A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:
1 day
24
7 day
24
3 3 days
7
4 days
Answer: Option
Explanation:
Formula: If A can do a piece of work in n days, then A's 1 day's work = 1 .
n

(A + B + C)'s 1 day's work = 1 + 1 + 1 = 7 .
24 6 12 24

Formula: If A's 1 day's work = 1 , then A can finish the work in n days.
n

So, all the three together will complete the job in 24 days = 3 3 days.
7 7

Discussion:
24 comments Page 2 of 3.

Seshapriya said:   1 decade ago
24*6 + 6*12 + 12*24 / 24*6*12 =144+72+288 / 1728

=504/1728

i.e

1728/504 days
24/7=

= 3 3/7 days option c..........

Swetha said:   1 decade ago
Given:

A can do a work in 24 days
B can do a work in 6 days
C can do a work in 12 days

Take LCM for 24,6 & 12 i.e 24
total work = 24
A's per day capacity = 24/24 = 1
B's per day capacity = 24/6 = 4
C's per day capacity = 24/12 = 2

If all working together,
their per day capacity = 1+4+2 = 7
all together will complete the work in 24/7 = 3 3/7 days

Sarthak said:   1 decade ago
Why did you ppl Reciprocal 7/24 ?

Aditya said:   1 decade ago
Thank you dharma you helped me alot.

Dharma said:   1 decade ago
A's work be x,
B's work be y
C's work be z

Total work done by A,B,C(A+B+C)=(X*Y*Z)/(XY+YZ+XZ)

Solution is:
x=12
y=6
z=24

A+B+C=(12*6*24)/(12*6+6*24+24*12)

= 24/7

= 3 and (3/7)

Mohit said:   2 decades ago
Hey look at the question first he is asking days for completion of work so If A's 1 day's work = 1/n then A can finish the work in n days its reciprocal of it.

Maheswari said:   2 decades ago
i can't get... how 1/n

Muthukumar said:   2 decades ago
I am not understand how to you got 7/24.

Sanjukta Nayak said:   2 decades ago
Me confused,please help

Simon said:   2 decades ago
I didn't get how you got 7/24.