Aptitude - Pipes and Cistern - Discussion
Discussion Forum : Pipes and Cistern - General Questions (Q.No. 15)
15.
Three pipes A, B and C can fill a tank in 6 hours. After working at it together for 2 hours, C is closed and A and B can fill the remaining part in 7 hours. The number of hours taken by C alone to fill the tank is:
Answer: Option
Explanation:
Part filled in 2 hours = | 2 | = | 1 |
6 | 3 |
Remaining part = | ![]() |
1 - | 1 | ![]() |
= | 2 | . |
3 | 3 |
![]() |
2 |
3 |
(A + B)'s 1 hour's work = | 2 |
21 |
C's 1 hour's work = { (A + B + C)'s 1 hour's work } - { (A + B)'s 1 hour's work }
= | ![]() |
1 | - | 2 | ![]() |
= | 1 |
6 | 21 | 14 |
C alone can fill the tank in 14 hours.
Discussion:
44 comments Page 1 of 5.
Gaurav Gowardhan said:
10 months ago
A .+ B + C = 6 hrs
2 hrs = 1/3 work,
remaining = 2/3 work.
A+B, 2/3 work= 7 hrs,
Total work 3/3 i.e 1 = 7 hrs + 7/2 hrs = 21/2 hrs
Now consider LCM of A + B + C & A+B.
i.e 6 & 21/2 is 42
Taking efficiency: A + B + C = 7units
A+B = 4 units.
So C's efficiency= A+ B+C -( A+ B).
= 7-4 = 3.
Total work is LCM i.e 42 & efficiency of C is 3.
So total time= 42/3 = 14.
2 hrs = 1/3 work,
remaining = 2/3 work.
A+B, 2/3 work= 7 hrs,
Total work 3/3 i.e 1 = 7 hrs + 7/2 hrs = 21/2 hrs
Now consider LCM of A + B + C & A+B.
i.e 6 & 21/2 is 42
Taking efficiency: A + B + C = 7units
A+B = 4 units.
So C's efficiency= A+ B+C -( A+ B).
= 7-4 = 3.
Total work is LCM i.e 42 & efficiency of C is 3.
So total time= 42/3 = 14.
L BEHERA said:
3 years ago
In this case, take LCM of 6 and 7, that is 42 and assume total manpower day is 42, the efficiency of A+B+C is 42/6 = 7.
A, B, C did for 2 days that is 7 * 2 = 14 MD complete, remaining 42-14=28 MD done by A+B in 7hr, So, A+B efficiency is 28/7 = 4.
So, C's efficiency is 7 - 4 = 3.
C can complete total work by 42/3=14 days.
A, B, C did for 2 days that is 7 * 2 = 14 MD complete, remaining 42-14=28 MD done by A+B in 7hr, So, A+B efficiency is 28/7 = 4.
So, C's efficiency is 7 - 4 = 3.
C can complete total work by 42/3=14 days.
(24)
Abir said:
3 years ago
Three pipes can fill a pipe in 6 hours,
(A+B+C) * 6 -----> (1)
Again, 3 workers work for 2 hours altogether so,
(A+B+C) * 2 , But The rest of the work done by A+B together, (A+B) *7
so. (A+B+C) *2 + (A+B) * 7 -----> (2)
ATQ,
(A+B+C) *6 = (A+B+C)*2 + (A+B) * 7.
Solving the equation we will get = C : A+B :: 3 : 4 (put this value in 1 or 2).
putting the value in 1 we will get,
(4+3)*7 = 42, this is the total work.
C = 42/3 = 14 Hours (ans)
(A+B+C) * 6 -----> (1)
Again, 3 workers work for 2 hours altogether so,
(A+B+C) * 2 , But The rest of the work done by A+B together, (A+B) *7
so. (A+B+C) *2 + (A+B) * 7 -----> (2)
ATQ,
(A+B+C) *6 = (A+B+C)*2 + (A+B) * 7.
Solving the equation we will get = C : A+B :: 3 : 4 (put this value in 1 or 2).
putting the value in 1 we will get,
(4+3)*7 = 42, this is the total work.
C = 42/3 = 14 Hours (ans)
(7)
Dipali Toraskar said:
4 years ago
Can you explain about the Remaining part?
(1)
Abhijeet keshri said:
5 years ago
It can be done very easily by the LCM method. Let the capacity of cistern be 42 units LCM of 6, 2 , 7. Then according to question.
A+B+C fills 7 units per hour(42/6). hence in 2 hours of operation, they fill 14 units.
Remaining units 42"14 = 28, which A+B fills in 7 hours means A+B fills 4 units per hour. hence it is clear that C fills 3 units per hour. So, C will fill the cisterns i.e. 42 units in 42/3 = 14 Hours.
A+B+C fills 7 units per hour(42/6). hence in 2 hours of operation, they fill 14 units.
Remaining units 42"14 = 28, which A+B fills in 7 hours means A+B fills 4 units per hour. hence it is clear that C fills 3 units per hour. So, C will fill the cisterns i.e. 42 units in 42/3 = 14 Hours.
(7)
Abhijeet keshri said:
5 years ago
It can be done very easily by the LCM method. Let the capacity of cistern be 42 units LCM of 6, 2 , 7. Then according to question.
A+B+C fills 7 units per hour(42/6). hence in 2 hours of operation, they fill 14 units.
Remaining units 42"14 = 28, which A+B fills in 7 hours means A+B fills 4 units per hour. hence it is clear that C fills 3 units per hour. So, C will fill the cisterns i.e. 42 units in 42/3 = 14 Hours.
A+B+C fills 7 units per hour(42/6). hence in 2 hours of operation, they fill 14 units.
Remaining units 42"14 = 28, which A+B fills in 7 hours means A+B fills 4 units per hour. hence it is clear that C fills 3 units per hour. So, C will fill the cisterns i.e. 42 units in 42/3 = 14 Hours.
(2)
Jigme Wangchuk said:
5 years ago
How 1/6 - 2/21 = 1 /14? Explain please.
Varidhi Deshpande said:
5 years ago
This can be easily solved.
1/A + 1/B + 1/C = 1/6.
1/A + 1/B = 1/6 - 1/C.
Therefore, a+b+c worked for 2hrs + a+b worked for 7hrs ( a+b=1/6 - 1/c) = Total work i.e., 1
i.e., 2(1/6) + 7(1/6 - 1/C ) = 1.
2/ 6 - 7/6 -1 = 1/C.
c = 14.
1/A + 1/B + 1/C = 1/6.
1/A + 1/B = 1/6 - 1/C.
Therefore, a+b+c worked for 2hrs + a+b worked for 7hrs ( a+b=1/6 - 1/c) = Total work i.e., 1
i.e., 2(1/6) + 7(1/6 - 1/C ) = 1.
2/ 6 - 7/6 -1 = 1/C.
c = 14.
(3)
Surekha Merla said:
5 years ago
@All.
Here, I've taken tank capacity as 42 litres.
A + B + C = 6 hours.
Remaining part by A + B in 7 hours.
So, LCM of 6 and 7 is 42.
If we take LCM's, cancellations will be easy in further steps.
Here, I've taken tank capacity as 42 litres.
A + B + C = 6 hours.
Remaining part by A + B in 7 hours.
So, LCM of 6 and 7 is 42.
If we take LCM's, cancellations will be easy in further steps.
Surekha Merla said:
5 years ago
Let's take tank capacity as 42 litres.
Given A+B+C finishes in 6 hours.
Per hour, A+B+C= 42/6 = 7 litres/hour.
But, They worked together for only 2 hours.
For 2 hours,
A+B+C= 7 litres => 2 hours=14litres/2hrs.
Remaining= 28 litres.
(A+B) worked to finish it in 7 hours.
So, (A+B)= 28/7 = 4 litres/hour.
Normally, (A+B)+C= 42/6 = 7 litres/hr.
In this one hour, (A+B) will fill 4 litres.
Remaining 3 litres will be filled by C in 1 hour.
So, C alone = 42/3= 14 hours.
Given A+B+C finishes in 6 hours.
Per hour, A+B+C= 42/6 = 7 litres/hour.
But, They worked together for only 2 hours.
For 2 hours,
A+B+C= 7 litres => 2 hours=14litres/2hrs.
Remaining= 28 litres.
(A+B) worked to finish it in 7 hours.
So, (A+B)= 28/7 = 4 litres/hour.
Normally, (A+B)+C= 42/6 = 7 litres/hr.
In this one hour, (A+B) will fill 4 litres.
Remaining 3 litres will be filled by C in 1 hour.
So, C alone = 42/3= 14 hours.
(2)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers