Aptitude - Chain Rule - Discussion
Discussion Forum : Chain Rule - General Questions (Q.No. 6)
6.
A man completes
of a job in 10 days. At this rate, how many more days will it takes him to finish the job?
of a job in 10 days. At this rate, how many more days will it takes him to finish the job?
Answer: Option
Explanation:
| Work done = | 5 |
| 8 |
| Balance work = | ![]() |
1 - | 5 | ![]() |
= | 3 |
| 8 | 8 |
Let the required number of days be x.
| Then, | 5 | : | 3 | = :: 10 : x | |
5 | x x = | 3 | x 10 |
| 8 | 8 | 8 | 8 |
x = |
![]() |
3 | x 10 x | 8 | ![]() |
| 8 | 5 |
x = 6.
Discussion:
36 comments Page 4 of 4.
Jefferson said:
7 years ago
5/8 of the work is completed in 10 days.
So we get the remaining work = (1-5/8).
= 3/8.
Completing work is directly proportional to days.
Hence direct proportion where x/y = constant.
Let we take the time taken to complete 3/8 be x.
And therefore = 10/(5/8) = 16,
for 3/8=8x/3,
thus 8x/3=16,
8x = 48,
and x = 6days.
So we get the remaining work = (1-5/8).
= 3/8.
Completing work is directly proportional to days.
Hence direct proportion where x/y = constant.
Let we take the time taken to complete 3/8 be x.
And therefore = 10/(5/8) = 16,
for 3/8=8x/3,
thus 8x/3=16,
8x = 48,
and x = 6days.
GAGAn said:
5 years ago
5/8 of the work could be completed in 10 days.
So, full work could be completed in 10*8/5 = 16 days.
Extra days = 16 -10 = 6 days.
So, full work could be completed in 10*8/5 = 16 days.
Extra days = 16 -10 = 6 days.
(1)
Anushree said:
4 years ago
@All.
Simply;
First of all, we need to divide 5 by 10, the answer will be 0.5/half so we need to draw two lines for each day, for ex ll-1,ll-2 etc.
And after it comes to 5 just continue drawing two lines for a day (so we will do like this- ll-6, ll-7 and ll-8 )
Now we need to see the number of lines we have drawn, that is 6, then the answer will be 6.
Thank you.
Simply;
First of all, we need to divide 5 by 10, the answer will be 0.5/half so we need to draw two lines for each day, for ex ll-1,ll-2 etc.
And after it comes to 5 just continue drawing two lines for a day (so we will do like this- ll-6, ll-7 and ll-8 )
Now we need to see the number of lines we have drawn, that is 6, then the answer will be 6.
Thank you.
Revanth said:
4 years ago
5/8 in 10 days.
So remaining 3/8.
10*3/8 ÷ 5/8 = 10 * 3 * 8/8 * 5 = 6 days.
So remaining 3/8.
10*3/8 ÷ 5/8 = 10 * 3 * 8/8 * 5 = 6 days.
(2)
Chophel said:
3 years ago
He completes 5/8 of the work in 10 days.
He can complete the work in
8/5 * 10 days,
= 80/5 days.
= 16 days.
He completed 10 days of work.
16-10= 6 days.
He can complete the work in
8/5 * 10 days,
= 80/5 days.
= 16 days.
He completed 10 days of work.
16-10= 6 days.
(6)
Chandan said:
5 months ago
He completes 5/8 of the work in 10 days.
He can complete the work in,
8/5 * 10 days,
= 80/5 days.
= 16 days.
He completed 10 days of work.
16 - 10 = 6 days.
He can complete the work in,
8/5 * 10 days,
= 80/5 days.
= 16 days.
He completed 10 days of work.
16 - 10 = 6 days.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers

