Aptitude - Chain Rule - Discussion

Discussion Forum : Chain Rule - General Questions (Q.No. 6)
6.
A man completes of a job in 10 days. At this rate, how many more days will it takes him to finish the job?
5
6
7
7 1
2
Answer: Option
Explanation:

Work done = 5
8

Balance work = 1 - 5 = 3
8 8

Let the required number of days be x.

Then, 5 : 3 = :: 10 : x     5 x x = 3 x 10
8 8 8 8

x = 3 x 10 x 8
8 5

x = 6.

Discussion:
36 comments Page 3 of 4.

Gokul raj said:   9 years ago
The work of 5 parts done in 10 days.
So, 10/5 = 2 days of time taken to complete one part.
Then, 5/8 has 3 remain parts 3 * 2(days) = 6 days.

Thank you.

Ram said:   9 years ago
Total work of job = 8,

Out of 8 he does 5 in 10 days (given in the question).

So, 5 work of a job = 10 days,

Therefore, 1 work of a job = 10/5 = 2 days,

Now remaining work are (8-5) = 3,

1 work = 2 days,

So, 3 work of a job = 3*2 = 6 days. (2+2+2).

Pavan Power star PK fan said:   9 years ago
He takes 10 days to complete 5/8 of the job.

In 1 day he does 5/80 of job.
If the job is complete then fraction will become 1.So (work done in 1 day) * (no. of days ) = 1.
Then, the number of days = 16.

But he did 10 days work already so the remaining days needed to complete the job is 6 days.

Zareena said:   8 years ago
5/8 job = 10 days,
1 job = 10 * 8/5,
1 job = 16 days,
16 - 10 days = 6 days.

Ram said:   8 years ago
Look another eg;

1/2 work = 5 day
Then,
Getting completed ie,
LHS should be 1.
cross multiply.
ie
1=2*5.
=10days.
Similarly,
5/8=10.
1= 8/5*10.
= 16.

Sowmiya said:   8 years ago
Very nice explanation @Bhadra.

Shubham said:   7 years ago
A garrison of 750 men has provision for 20 weeks if, at the end of 4 weeks, they are reinforced by 450 men, how long the provision will last?

How to solve this by using the chain rule? Please help me.

Venkat Ravi said:   7 years ago
Consider a job value is 100(not given).

8/3 of work is done in 10 days then,

(8/3)*100 = 62.5(ie.,62.5% of work is completed in 10 days then the remaining work will be 37.5).

For 10 days 67.5.
For single day=(67.5/10)=6.75(ie.,per day work).
Remaining days=(remaining work/per day work) = (37.5/6.75) = 6 days.

RAJAN said:   6 years ago
He completed 5 jobs out of 8, in 10 days so that means he completed 1 job in 2 days and to complete 3 more jobs (8-5=3) and he will take 6 days (3x2=6).
(2)

Pujan Das said:   6 years ago
5/8 is completed in 10 days.
Hence, 1 (100%) will be completed in (10*8)/5 = 16 days.
The rate of work remains constant. (important point).
Thus, Remaining days = total days - elapsed = 16 - 10 = 6 days.


Post your comments here:

Your comments will be displayed after verification.