Aptitude - Chain Rule - Discussion
Discussion Forum : Chain Rule - General Questions (Q.No. 6)
6.
A man completes
of a job in 10 days. At this rate, how many more days will it takes him to finish the job?
of a job in 10 days. At this rate, how many more days will it takes him to finish the job?
Answer: Option
Explanation:
| Work done = | 5 |
| 8 |
| Balance work = | ![]() |
1 - | 5 | ![]() |
= | 3 |
| 8 | 8 |
Let the required number of days be x.
| Then, | 5 | : | 3 | = :: 10 : x | |
5 | x x = | 3 | x 10 |
| 8 | 8 | 8 | 8 |
x = |
![]() |
3 | x 10 x | 8 | ![]() |
| 8 | 5 |
x = 6.
Discussion:
37 comments Page 1 of 4.
Raji said:
1 week ago
5/8 th of the work in 10 days.
(1-5/8) = 3/8 th of the work in 'x' days.
cross multiplication : 5/8 --> 10.
3/8 --> x.
5/8 * x = 3/8 * 10.
x = 6.
(1-5/8) = 3/8 th of the work in 'x' days.
cross multiplication : 5/8 --> 10.
3/8 --> x.
5/8 * x = 3/8 * 10.
x = 6.
Chandan said:
9 months ago
He completes 5/8 of the work in 10 days.
He can complete the work in,
8/5 * 10 days,
= 80/5 days.
= 16 days.
He completed 10 days of work.
16 - 10 = 6 days.
He can complete the work in,
8/5 * 10 days,
= 80/5 days.
= 16 days.
He completed 10 days of work.
16 - 10 = 6 days.
(1)
Chophel said:
4 years ago
He completes 5/8 of the work in 10 days.
He can complete the work in
8/5 * 10 days,
= 80/5 days.
= 16 days.
He completed 10 days of work.
16-10= 6 days.
He can complete the work in
8/5 * 10 days,
= 80/5 days.
= 16 days.
He completed 10 days of work.
16-10= 6 days.
(6)
Revanth said:
4 years ago
5/8 in 10 days.
So remaining 3/8.
10*3/8 ÷ 5/8 = 10 * 3 * 8/8 * 5 = 6 days.
So remaining 3/8.
10*3/8 ÷ 5/8 = 10 * 3 * 8/8 * 5 = 6 days.
(2)
Anushree said:
4 years ago
@All.
Simply;
First of all, we need to divide 5 by 10, the answer will be 0.5/half so we need to draw two lines for each day, for ex ll-1,ll-2 etc.
And after it comes to 5 just continue drawing two lines for a day (so we will do like this- ll-6, ll-7 and ll-8 )
Now we need to see the number of lines we have drawn, that is 6, then the answer will be 6.
Thank you.
Simply;
First of all, we need to divide 5 by 10, the answer will be 0.5/half so we need to draw two lines for each day, for ex ll-1,ll-2 etc.
And after it comes to 5 just continue drawing two lines for a day (so we will do like this- ll-6, ll-7 and ll-8 )
Now we need to see the number of lines we have drawn, that is 6, then the answer will be 6.
Thank you.
GAGAn said:
6 years ago
5/8 of the work could be completed in 10 days.
So, full work could be completed in 10*8/5 = 16 days.
Extra days = 16 -10 = 6 days.
So, full work could be completed in 10*8/5 = 16 days.
Extra days = 16 -10 = 6 days.
(1)
Jefferson said:
7 years ago
5/8 of the work is completed in 10 days.
So we get the remaining work = (1-5/8).
= 3/8.
Completing work is directly proportional to days.
Hence direct proportion where x/y = constant.
Let we take the time taken to complete 3/8 be x.
And therefore = 10/(5/8) = 16,
for 3/8=8x/3,
thus 8x/3=16,
8x = 48,
and x = 6days.
So we get the remaining work = (1-5/8).
= 3/8.
Completing work is directly proportional to days.
Hence direct proportion where x/y = constant.
Let we take the time taken to complete 3/8 be x.
And therefore = 10/(5/8) = 16,
for 3/8=8x/3,
thus 8x/3=16,
8x = 48,
and x = 6days.
Pujan Das said:
7 years ago
5/8 is completed in 10 days.
Hence, 1 (100%) will be completed in (10*8)/5 = 16 days.
The rate of work remains constant. (important point).
Thus, Remaining days = total days - elapsed = 16 - 10 = 6 days.
Hence, 1 (100%) will be completed in (10*8)/5 = 16 days.
The rate of work remains constant. (important point).
Thus, Remaining days = total days - elapsed = 16 - 10 = 6 days.
RAJAN said:
7 years ago
He completed 5 jobs out of 8, in 10 days so that means he completed 1 job in 2 days and to complete 3 more jobs (8-5=3) and he will take 6 days (3x2=6).
(2)
Venkat Ravi said:
8 years ago
Consider a job value is 100(not given).
8/3 of work is done in 10 days then,
(8/3)*100 = 62.5(ie.,62.5% of work is completed in 10 days then the remaining work will be 37.5).
For 10 days 67.5.
For single day=(67.5/10)=6.75(ie.,per day work).
Remaining days=(remaining work/per day work) = (37.5/6.75) = 6 days.
8/3 of work is done in 10 days then,
(8/3)*100 = 62.5(ie.,62.5% of work is completed in 10 days then the remaining work will be 37.5).
For 10 days 67.5.
For single day=(67.5/10)=6.75(ie.,per day work).
Remaining days=(remaining work/per day work) = (37.5/6.75) = 6 days.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers

