Aptitude - Chain Rule - Discussion

Discussion Forum : Chain Rule - General Questions (Q.No. 6)
6.
A man completes of a job in 10 days. At this rate, how many more days will it takes him to finish the job?
5
6
7
7 1
2
Answer: Option
Explanation:

Work done = 5
8

Balance work = 1 - 5 = 3
8 8

Let the required number of days be x.

Then, 5 : 3 = :: 10 : x     5 x x = 3 x 10
8 8 8 8

x = 3 x 10 x 8
8 5

x = 6.

Discussion:
36 comments Page 1 of 4.

Chandan said:   2 months ago
He completes 5/8 of the work in 10 days.
He can complete the work in,
8/5 * 10 days,
= 80/5 days.
= 16 days.

He completed 10 days of work.
16 - 10 = 6 days.

Chophel said:   3 years ago
He completes 5/8 of the work in 10 days.
He can complete the work in
8/5 * 10 days,
= 80/5 days.
= 16 days.

He completed 10 days of work.
16-10= 6 days.
(6)

Revanth said:   3 years ago
5/8 in 10 days.

So remaining 3/8.
10*3/8 ÷ 5/8 = 10 * 3 * 8/8 * 5 = 6 days.
(1)

Anushree said:   3 years ago
@All.

Simply;

First of all, we need to divide 5 by 10, the answer will be 0.5/half so we need to draw two lines for each day, for ex ll-1,ll-2 etc.

And after it comes to 5 just continue drawing two lines for a day (so we will do like this- ll-6, ll-7 and ll-8 )

Now we need to see the number of lines we have drawn, that is 6, then the answer will be 6.

Thank you.

GAGAn said:   5 years ago
5/8 of the work could be completed in 10 days.
So, full work could be completed in 10*8/5 = 16 days.
Extra days = 16 -10 = 6 days.
(1)

Jefferson said:   6 years ago
5/8 of the work is completed in 10 days.
So we get the remaining work = (1-5/8).
= 3/8.
Completing work is directly proportional to days.

Hence direct proportion where x/y = constant.
Let we take the time taken to complete 3/8 be x.
And therefore = 10/(5/8) = 16,
for 3/8=8x/3,
thus 8x/3=16,
8x = 48,
and x = 6days.

Pujan Das said:   6 years ago
5/8 is completed in 10 days.
Hence, 1 (100%) will be completed in (10*8)/5 = 16 days.
The rate of work remains constant. (important point).
Thus, Remaining days = total days - elapsed = 16 - 10 = 6 days.

RAJAN said:   6 years ago
He completed 5 jobs out of 8, in 10 days so that means he completed 1 job in 2 days and to complete 3 more jobs (8-5=3) and he will take 6 days (3x2=6).
(2)

Venkat Ravi said:   7 years ago
Consider a job value is 100(not given).

8/3 of work is done in 10 days then,

(8/3)*100 = 62.5(ie.,62.5% of work is completed in 10 days then the remaining work will be 37.5).

For 10 days 67.5.
For single day=(67.5/10)=6.75(ie.,per day work).
Remaining days=(remaining work/per day work) = (37.5/6.75) = 6 days.

Shubham said:   7 years ago
A garrison of 750 men has provision for 20 weeks if, at the end of 4 weeks, they are reinforced by 450 men, how long the provision will last?

How to solve this by using the chain rule? Please help me.


Post your comments here:

Your comments will be displayed after verification.