Aptitude - Chain Rule - Discussion

Discussion Forum : Chain Rule - General Questions (Q.No. 6)
6.
A man completes of a job in 10 days. At this rate, how many more days will it takes him to finish the job?
5
6
7
7 1
2
Answer: Option
Explanation:

Work done = 5
8

Balance work = 1 - 5 = 3
8 8

Let the required number of days be x.

Then, 5 : 3 = :: 10 : x     5 x x = 3 x 10
8 8 8 8

x = 3 x 10 x 8
8 5

x = 6.

Discussion:
36 comments Page 2 of 4.

Sowmiya said:   8 years ago
Very nice explanation @Bhadra.

Ram said:   8 years ago
Look another eg;

1/2 work = 5 day
Then,
Getting completed ie,
LHS should be 1.
cross multiply.
ie
1=2*5.
=10days.
Similarly,
5/8=10.
1= 8/5*10.
= 16.

Zareena said:   8 years ago
5/8 job = 10 days,
1 job = 10 * 8/5,
1 job = 16 days,
16 - 10 days = 6 days.

Pavan Power star PK fan said:   9 years ago
He takes 10 days to complete 5/8 of the job.

In 1 day he does 5/80 of job.
If the job is complete then fraction will become 1.So (work done in 1 day) * (no. of days ) = 1.
Then, the number of days = 16.

But he did 10 days work already so the remaining days needed to complete the job is 6 days.

Ram said:   9 years ago
Total work of job = 8,

Out of 8 he does 5 in 10 days (given in the question).

So, 5 work of a job = 10 days,

Therefore, 1 work of a job = 10/5 = 2 days,

Now remaining work are (8-5) = 3,

1 work = 2 days,

So, 3 work of a job = 3*2 = 6 days. (2+2+2).

Gokul raj said:   9 years ago
The work of 5 parts done in 10 days.
So, 10/5 = 2 days of time taken to complete one part.
Then, 5/8 has 3 remain parts 3 * 2(days) = 6 days.

Thank you.

Bindu brisk said:   9 years ago
It's so simple:

Total of 8 parts 5 parts done in 10 days:

Remaining 3 parts in 6 days:

1 part = 2 days.

Kathik said:   10 years ago
Given that 5/8 (job) = 10 days.

Then for full job completion take:

1(job) = 10(8/5).

= 16 days.

So in question asked how many remaining days to finish the job.

So Total days - Given days.

= 16 - 10 = 6 days.

Gaurav Pant said:   1 decade ago
5/8 work completed in 10 days.

Total work will complete = 10*(8/5) = 80/5 = 16.

Therefore remaining work (1-5/8) done on = 16-10 days = 6 days.

Sankar said:   1 decade ago
A's 10 days work 5/8.

Then A's one day 5/10 = 0.50.

Remaining work 3/8. So 2 days 1 work over.

Therefore remaining work is 3*2 = 6 days remaining over.


Post your comments here:

Your comments will be displayed after verification.