9. 

The correct sequence of phases in value engineering is

[A]. creative phase, information phase, investigation phase, evaluation phase
[B]. information phase, creative phase, investigation phase, evaluation phase
[C]. investigation phase, information phase, creative phase, evaluation phase
[D]. creative phase, investigation phase, evaluation phase, information phase

Answer: Option A

Explanation:

No answer description available for this question.

Imap said: (Jul 31, 2015)  
This is wrong. Correct sequence shown below.

1. Information phase.
2. Creative phase.
3. Investigation phase.
4. Evaluation phase.

Jay said: (Oct 6, 2016)  
Answer should be option B.

Prince said: (Feb 9, 2017)  
BLAST --CREATE-- DEFINE.

B is correct.

Pankaj said: (Jun 13, 2017)  
The Answer must be B.