7.
Scheduling
prescribes the sequence of operations to be followed
determines the programme for the operations
is concerned with starting of processes
regulates the progress of job through various processes
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
12 comments Page 2 of 2.

Suraj Nanaware said:   6 years ago
Option A is Routing - which describes path and sequence of operation.

Yash said:   6 years ago
Routing - prescribes the sequence of operations to be followed.

Scheduling - determines the programme for the operations.

Dispatching - is concerned with the starting of processes.

Followup - regulates the progress of the job through various processes.