Mechanical Engineering - Industrial Engineering and Production Management - Discussion

7. 

Scheduling

[A]. prescribes the sequence of operations to be followed
[B]. determines the programme for the operations
[C]. is concerned with starting of processes
[D]. regulates the progress of job through various processes

Answer: Option B

Explanation:

No answer description available for this question.

Prince said: (Feb 9, 2017)  
According to me, A is correct.

Venky said: (Apr 6, 2017)  
I think A is correct.

Vinit said: (Jun 19, 2017)  
The correct answer is A.

Tejas said: (Jun 21, 2017)  
I think A is correct.

Abhilash said: (Jun 29, 2017)  
Option A is correct.

Ganeswar Mardi said: (Jul 11, 2017)  
I think A should be the answer.

Sneha said: (Aug 2, 2017)  
I think A) routing.

Abel said: (Nov 24, 2018)  
@Sneha.

Option A is planning not routing.

Mak said: (Jan 24, 2019)  
Option A is routing. I agree.

Subodh Kumar said: (Mar 13, 2019)  
A is routing.

It determines how and where the work is to be done, what machines are to be used and it prescribes the path and sequence of operation to be followed.

Suraj Nanaware said: (Jul 8, 2019)  
Option A is Routing - which describes path and sequence of operation.

Yash said: (Feb 20, 2020)  
Routing - prescribes the sequence of operations to be followed.

Scheduling - determines the programme for the operations.

Dispatching - is concerned with the starting of processes.

Followup - regulates the progress of the job through various processes.

Post your comments here: