Discussion Forum : Industrial Engineering and Production Management - Section 2 (Q.No. 48)
48.
The average time recorded by work study man for an operation is called
Discussion:
2 comments Page 1 of 1.
Nvk said:
12 months ago
The correct answer is: standard time.
The average time recorded by a work-study man (or industrial engineer) for an operation is called standard time. Standard time is the time required to complete a task or operation, taking into account:
- The skill and ability of the worker
- The tools and equipment used
- The working conditions
- The allowed allowances (e.g., rest, breaks)
Standard time is used to:
- Establish a fair and realistic target time for workers
- Set production standards
- Measure worker performance
- Identify areas for improvement
The other options are not correct:
- Normal time refers to the actual time taken by a worker to complete a task, which may vary from standard time.
- Representative time is not a commonly used term in work-study or industrial engineering.
=> Standard time is an important concept in work-study and industrial engineering, as it helps to establish a baseline for measuring performance and identifying opportunities for improvement.
The average time recorded by a work-study man (or industrial engineer) for an operation is called standard time. Standard time is the time required to complete a task or operation, taking into account:
- The skill and ability of the worker
- The tools and equipment used
- The working conditions
- The allowed allowances (e.g., rest, breaks)
Standard time is used to:
- Establish a fair and realistic target time for workers
- Set production standards
- Measure worker performance
- Identify areas for improvement
The other options are not correct:
- Normal time refers to the actual time taken by a worker to complete a task, which may vary from standard time.
- Representative time is not a commonly used term in work-study or industrial engineering.
=> Standard time is an important concept in work-study and industrial engineering, as it helps to establish a baseline for measuring performance and identifying opportunities for improvement.
Measfin M said:
4 years ago
Standard time is right because it is the average time.