Discussion Forum : System Analysis and Design - Section 5 (Q.No. 19)
19.
Which of the following systems implementation approaches should be used if you want to run the old system and the new system at the same time for a specified period?
direct
pilot
phased
parallel
None of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.