5.
For laying a sewer line in a trench of 2 m width, an offset line is marked on the ground parallel to the given centre line at a distance of
100 cm
120 cm
140 cm
160 cm
180 cm.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
5 comments Page 1 of 1.

Daljeet Singh said:   8 years ago
Because this is long offset.
(1)

Dhanu said:   7 years ago
offset = half of trench width + 0.6m.
0ff = 1 + 0.6 =1.6m=160 cm.

Raj said:   6 years ago
Thank you for describing this.

Roy said:   6 years ago
The Formula is B/2 + 0.6.
(1)

S raju said:   6 years ago
Which diameter of the pipe is suitable for this trench?