Discussion Forum : Waste Water Engineering - Section 7 (Q.No. 5)
5.
For laying a sewer line in a trench of 2 m width, an offset line is marked on the ground parallel to the given centre line at a distance of
Discussion:
5 comments Page 1 of 1.
S raju said:
6 years ago
Which diameter of the pipe is suitable for this trench?
Roy said:
6 years ago
The Formula is B/2 + 0.6.
(1)
Raj said:
6 years ago
Thank you for describing this.
Dhanu said:
7 years ago
offset = half of trench width + 0.6m.
0ff = 1 + 0.6 =1.6m=160 cm.
0ff = 1 + 0.6 =1.6m=160 cm.
Daljeet Singh said:
8 years ago
Because this is long offset.
(1)