Civil Engineering - Waste Water Engineering - Discussion
Discussion Forum : Waste Water Engineering - Section 3 (Q.No. 35)
35.
The density of population over 40 hectares is 250/hectare. If water supply demand per day is 200 litres and sewage discharge is 80% of water supply, the sewage flow in sewers of separate system, is
Discussion:
18 comments Page 1 of 2.
Anila kumar mashyal said:
3 years ago
Total population = 250 * 40 = 10000.
Average sewage discharge per capita = 0.8 * 200 = 160 day/capita.
Average sewage flow generated by 10000 people = 160 * 10000 = 1600 m3/day.
Peak sewage = 3 times the average sewage = 3 * 1600 = 4800 m3/day.
Peak sewage in m3/s = 480024 * 3600 = 0.05556 m3/s.
Average sewage discharge per capita = 0.8 * 200 = 160 day/capita.
Average sewage flow generated by 10000 people = 160 * 10000 = 1600 m3/day.
Peak sewage = 3 times the average sewage = 3 * 1600 = 4800 m3/day.
Peak sewage in m3/s = 480024 * 3600 = 0.05556 m3/s.
(8)
MILI said:
3 years ago
1000 in the denominator is for converting litres to meter cube.
(2)
Anirban Roy said:
5 years ago
Right @Debsubhra.
Debsubhra pal said:
5 years ago
The Design discharge is 6*dwf.
Hemanta said:
6 years ago
Sewer is designed on the basis of maximum hourly flow.
That's why we need to multiply 0.0185 with 3.
= (0.0185*3) = 0.05556 cumec.
That's why we need to multiply 0.0185 with 3.
= (0.0185*3) = 0.05556 cumec.
Raj said:
7 years ago
Thank you for giving the explanation.
Akash said:
8 years ago
It should be 0.0185 cu.m/sec.
Anju said:
8 years ago
Yes, right @Anand and @Chaya.
Chayya said:
8 years ago
Yes, right @Anand.
3 is a safety factor in a sewer.
3 is a safety factor in a sewer.
Niranjan said:
9 years ago
Great section, thanks to all.