7.
The optimistic, most likely and pessimistic time estimates of an activity are 5, 10 and 21 days respectively. What are the expected time and standard deviation ?
12, 3
11, 4
11,
10, 16
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

Sai harshith said:   3 years ago
12, 3 is the right answer.
Te = (5+4*10+21)/6 = 11.66 = 12.
Standard deviation = (21-5)/6 = 2.67 = 3.

Karan said:   8 years ago
Expected time = (5+4 * 10 + 21)/6 = 11.

Standard deviation = (21-5)/6 = 2.67.